16107 W VICTORY BLVD 91406
Certificate Information: 16107 W VICTORY BLVD 91406
- Application / Permit
- 24016-20000-36285
- Plan Check / Job No.
- B24VN22873
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- TENANT IMPROVEMENT TO EXISTING MARKET, ADDITION OF METAL CANOPY OVER THE LOADING DOCK, REMODELING OF EXISTING MEZZANINE AND EXTERIOR ALTERATIONNO CHANGE OF USE.
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 11/14/2024 | FRANCIS AHN |
| Corrections Issued | 11/19/2024 | HERNAN ARREOLA |
| Quality Review Completed | 11/20/2024 | PETER KIM |
| Applicant returned to address corrections | 1/16/2025 | HERNAN ARREOLA |
| Plan Check Approved | 1/31/2025 | HERNAN ARREOLA |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 7/9/2025 | DANIEL VARNUM |
| Permit Finaled | 7/10/2025 | JEFFREY DURAN |
| CofO Issued | 7/10/2025 | JEFFREY DURAN |
| Permit Finaled | 7/10/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 12/26/2024 | MICHAEL AYERS |
| Zoning Plan Check | Cleared | 12/27/2024 | NICOLE WIDJAJA |
| DAS Clearance | Cleared | 1/14/2025 | Jesse Arellano |
Contact Information
| Contractor | Kirkley Corporation Inc; Lic. No.: 408026-B | , |
| Engineer | Jafari,, Masoud -; Lic. No.: NA3812 | , |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 2/21/2025 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 3/3/2025 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 3/4/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/5/2025 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 3/11/2025 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 3/20/2025 | Conditional Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 3/21/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/25/2025 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 3/26/2025 | Partial Approval | BRIAN KELLY |
| Wood Frame | 3/26/2025 | Partial Inspection | BRIAN KELLY |
| Deputy Steel/Welding | 4/2/2025 | Conditional Approval | GREGORY POMISH |
| Drywall Nailing | 4/3/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 4/8/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Structural Steel Frame | 4/9/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 4/14/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 4/23/2025 | Approved | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 4/23/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 4/25/2025 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 4/30/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 5/2/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 5/15/2025 | Conditional Approval | KENNETH ROBERTS |
| T-Bar Ceiling | 6/5/2025 | Approved | DANIEL VARNUM |
| Pre-Inspection | 6/12/2025 | Partial Approval | DANIEL VARNUM |
| Final | 6/26/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 6/26/2025 | Approved | DANIEL VARNUM |
| Green Building Rough | 6/26/2025 | Approved | DANIEL VARNUM |
| Reinforced Masonry Frame | 6/26/2025 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 6/26/2025 | Approved | DANIEL VARNUM |
| Final | 7/3/2025 | Partial Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 7/3/2025 | Partial Inspection | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/10/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 7/10/2025 | Conditional Approval | DANIEL VARNUM |
| Final | 7/10/2025 | OK to Issue CofO | DANIEL VARNUM |