19950 W RINALDI ST 91326
Certificate Information: 19950 W RINALDI ST 91326
- Application / Permit
- 24016-20000-36283
- Plan Check / Job No.
- B24VN22864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- TENANT IMPROVEMENT TO (E) MEDICAL OFFICE
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Metro
- Current Status
- Issued on 5/7/2025
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Zoning Architect | 11/14/2024 | JASON BRAVO |
| Assigned to Plan Check Engineer | 11/26/2024 | MARVEL DELACRUZ |
| Corrections Issued | 12/4/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 12/5/2024 | JASON HEALEY |
| Building Plans Picked Up | 12/9/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 1/21/2025 | APPLICANT |
| Green Plans Picked Up | 1/21/2025 | APPLICANT |
| Plan Check Approved | 4/17/2025 | MARVEL DELACRUZ |
| Issued | 5/7/2025 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/27/2025 | MARVEL DELACRUZ |
| Miscellaneous | Cleared | 2/27/2025 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 2/27/2025 | ASHLEY RODARTE |
| Green Code | Cleared | 2/28/2025 | MICHAEL AYERS |
| Zoning Plan Check | Cleared | 3/20/2025 | JASON BRAVO |
Contact Information
| Architect | Dong,, Heney; Lic. No.: C9770 | 23901 CALABASAS RD #1083 CALABASAS, CA 91302 |
| Contractor | Con - Am Inc; Lic. No.: 698311-B | 903 CALLE AMANECER STE 210 SAN CLEMENTE, CA 92673 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/30/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 5/30/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 6/26/2025 | Partial Approval | DEANDRE HOFFMAN |
| Wall Anchors | 6/26/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/30/2025 | Approved | GREGORY POMISH |
| Reinforced Concrete Frame | 6/30/2025 | Approved | GREGORY POMISH |
| Drywall Nailing | 7/15/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 8/6/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Drywall Nailing | 8/13/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 8/19/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 8/29/2025 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 8/29/2025 | Approved | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 10/3/2025 | Not Ready for Inspection | GREGORY POMISH |
| Light Gage Steel Frame | 10/6/2025 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 10/10/2025 | Partial Approval | GREGORY POMISH |
| T-Bar Ceiling | 10/27/2025 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 11/14/2025 | Approved | DEANDRE HOFFMAN |
| Structural Steel Frame | 11/25/2025 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 12/5/2025 | Approved | DEANDRE HOFFMAN |
| Final | 12/19/2025 | No Access for Inspection | BRIAN KELLY |
| Green Building Final | 12/19/2025 | No Access for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/19/2025 | No Access for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 1/14/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 1/22/2026 | Approved | GREGORY POMISH |
| T-Bar Ceiling | 2/17/2026 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 4/3/2026 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 4/7/2026 | Approved | GREGORY POMISH |
| Light Gage Steel Frame | 4/29/2026 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 4/29/2026 | Approved | EDWIN GREGORYONA |