22032 W COSTANSO ST 91364
Certificate Information: 22032 W COSTANSO ST 91364
- Application / Permit
- 24016-20000-36281
- Plan Check / Job No.
- B24VN22860
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE AND STORAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/23/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/25/2024 | APPLICANT |
| Issued | 12/31/2024 | APPLICANT |
| CofO in Progress | 12/19/2025 | JOHN HAYES |
| Permit Finaled | 2/10/2026 | JOHN JANSON |
| CofO Issued | 2/10/2026 | JOHN JANSON |
| Permit Finaled | 2/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/26/2024 | LEE GUILBEAUX |
| ZI | Cleared | 11/26/2024 | STEVEN WECHSLER |
| Grading Pre-Inspection | Cleared | 11/26/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/9/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 12/27/2024 | THERESA NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2025 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 1/6/2025 | Corrections Issued | JOHN HAYES |
| Wood Frame | 1/6/2025 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/16/2025 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 1/16/2025 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 1/16/2025 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 2/12/2025 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 4/4/2025 | Conditional Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/11/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 4/11/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Sewer | 4/11/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 4/17/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Underground Mechanical | 4/17/2025 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Gas Test | 5/5/2025 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/27/2025 | Approved | JOHN COLEMAN |
| Wood Frame | 6/23/2025 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 7/7/2025 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 7/7/2025 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/7/2025 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 7/7/2025 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 7/17/2025 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/25/2025 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Approved | SEAN WIRCH |
| HVAC-Rough | 7/25/2025 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 7/25/2025 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | JOHN HAYES |
| Green Building Rough | 8/8/2025 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/8/2025 | Approved | JOHN HAYES |
| Wood Frame | 8/8/2025 | Off-Hour Fees Due | |
| Insulation | 8/29/2025 | Approved | SCOTT SOBEL |
| Shower Pan | 8/29/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Drywall Nailing | 9/5/2025 | Approved | SCOTT SOBEL |
| Shower Pan | 9/5/2025 | Approved | SCOTT SOBEL |
| Insulation | 9/19/2025 | Corrections Issued | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/19/2025 | Approved | SCOTT SOBEL |
| Insulation | 9/22/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 12/3/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 12/3/2025 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 12/3/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 12/9/2025 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/9/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/9/2025 | Approved | JOHN HAYES |
| PLUMBING-Final | 12/9/2025 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 12/9/2025 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/9/2025 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 12/12/2025 | Approved | SEAN WIRCH |
| PLUMBING-Final | 12/12/2025 | Approved | SEAN WIRCH |
| Service/Power Release | 12/12/2025 | Approved | SEAN WIRCH |
| Final | 12/19/2025 | OK to Issue CofO | JOHN HAYES |