17042 W STRATHERN ST 91406

Certificate Information: 17042 W STRATHERN ST 91406

Application / Permit
24016-20000-36224
Plan Check / Job No.
B24VN22806
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) DETACHED ACCESSORY LIVING QUARTERS INTO A (N) 20-0" x 45'-4" 2ND DWELLING UNIT PER SB9-TWO UNIT DEVELOPMENT. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 5/22/2025
Issuing Office
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 ALFRED RAMIREZ
Corrections Issued 12/2/2024 ALFRED RAMIREZ
Quality Review Completed 12/5/2024 STEVEN KIM
Building Plans Picked Up 12/5/2024 APPLICANT
Applicant returned to address corrections 12/23/2024 ALFRED RAMIREZ
Plan Check Approved 5/22/2025 ALFRED RAMIREZ
Issued 5/22/2025 APPLICANT
CofO in Progress 9/15/2025 GAREN HAYRAPETYAN
CofO Issued 9/23/2025 RUBEN SALAS
Permit Finaled 9/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/9/2024 CARLOS AGUILERA
Senate Bill 9 Cleared 12/9/2024 ASHLEY RODARTE
Sewer availability Cleared 12/10/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/18/2024 CARLOS AGUILERA
Construction near power lines Cleared 5/19/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/29/2025 Corrections Issued SALVADOR MARTINEZ
Final 5/29/2025 Corrections Issued SALVADOR MARTINEZ
Smoke Detectors 5/29/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/29/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 8/29/2025 Corrections Issued GAREN HAYRAPETYAN
Smoke Detectors 8/29/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 9/4/2025 Approved GAREN HAYRAPETYAN
Gas Test 9/4/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 9/4/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 9/4/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 9/8/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/15/2025 Approved GAREN HAYRAPETYAN
Final 9/15/2025 OK to Issue CofO GAREN HAYRAPETYAN
Smoke Detectors 9/15/2025 Approved GAREN HAYRAPETYAN