10113 N KESTER AVE 91345
Certificate Information: 10113 N KESTER AVE 91345
- Application / Permit
- 24016-20000-36104
- Plan Check / Job No.
- B24VN22671
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REPAIR FIRED PORTION OF A WALL OF A TWO CARS GARAGE AND REBUILD THE WHOLE STRUCTURE OF THE ROOF OF THE EXITING TWO CARS GARAGE - PER ENGINEER
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Current Status
- Issued on 11/26/2024
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 11/18/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 11/25/2024 | DANIEL ABRAMYAN |
| Issued | 11/26/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/20/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | RYAN CASTRO |
Contact Information
| Contractor | Brosteem Builders Inc; Lic. No.: 779289-B | , |
| Contractor | Servicemaster By Russell T A; Lic. No.: 779289-B | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 3/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/28/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/3/2025 | Approved | JENNIFER RABUCHIN |