9304-9306 N GERALD AVE 91343

Certificate Information: 9304-9306 N GERALD AVE 91343

Application / Permit
24016-20000-36076
Plan Check / Job No.
B24VN22638
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 342.61 SQ. FT. PORTION OF THE (E) SFD INTO A (N) JR. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 . ALL WORK PER WFPP
Permit Issued
Issued on 11/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/12/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 11/12/2024 ARAMIK SHAHMIRZAIAN
Plan Check Approved 11/26/2024 ALEC MOUSAKHANIAN
Issued 11/26/2024 APPLICANT
CofO in Progress 4/23/2025 SALVADOR MARTINEZ
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/15/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2024 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 1/6/2025 Not Ready for Inspection SALVADOR MARTINEZ
Deputy Drilled-In Anchors 1/14/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 1/23/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 1/23/2025 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 1/23/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 1/23/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 2/3/2025 Partial Approval GAREN HAYRAPETYAN
HVAC-Rough 2/3/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 2/12/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/21/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 3/21/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/21/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 3/21/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 3/21/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV No Gas GAREN HAYRAPETYAN
Smoke Detectors 3/21/2025 Approved GAREN HAYRAPETYAN
Final 4/15/2025 Corrections Issued SALVADOR MARTINEZ
Final 4/22/2025 OK to Issue CofO SALVADOR MARTINEZ