18168 W TARZANA ST 91356

Certificate Information: 18168 W TARZANA ST 91356

Application / Permit
24016-20000-35949
Plan Check / Job No.
B24VN22616
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 1/17/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2024 APPLICANT
Assigned to Plan Check Engineer 11/18/2024 MIROOSH KHACHATOORIAN
Corrections Issued 11/18/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 11/22/2024 APPLICANT
Plan Check Approved 1/17/2025 ANGELICA MARTINEZ
Issued 1/17/2025 APPLICANT
CofO in Progress 8/13/2025 JOHN KIDWELL
Permit Finaled 8/22/2025 JOHN JANSON
CofO Issued 8/22/2025 JOHN JANSON
Permit Finaled 8/22/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/26/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/26/2024 RYAN CASTRO
Sewer availability Cleared 11/26/2024 RYAN CASTRO
Construction near power lines Cleared 12/19/2024 RIDWAN HARDY
Construction within easement Cleared 12/19/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 1/17/2025 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 2/19/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 2/19/2025 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 2/25/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 2/25/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 2/28/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 3/11/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval JOHN KIDWELL
Green Building Rough 3/11/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 3/18/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 4/1/2025 Approved JOHN KIDWELL
ELECTRICAL-Rough 4/1/2025 Approved JOHN KIDWELL
Gas Test 4/1/2025 Partial Approval JOHN KIDWELL
Green Building Rough 4/1/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/1/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 4/1/2025 Approved JOHN KIDWELL
Insulation 4/9/2025 Approved JOHN KIDWELL
Drywall Nailing 4/23/2025 Approved JOHN KIDWELL
Final 6/6/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 6/6/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 6/6/2025 Approved JOHN KIDWELL
Final 6/11/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 6/11/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved JOHN KIDWELL
Final 7/10/2025 OK to Issue CofO JOHN KIDWELL
Green Building Final 7/10/2025 Approved JOHN KIDWELL