18168 W TARZANA ST 91356
Certificate Information: 18168 W TARZANA ST 91356
- Application / Permit
- 24016-20000-35949
- Plan Check / Job No.
- B24VN22616
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 11/18/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 11/22/2024 | APPLICANT |
| Plan Check Approved | 1/17/2025 | ANGELICA MARTINEZ |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 8/13/2025 | JOHN KIDWELL |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
| CofO Issued | 8/22/2025 | JOHN JANSON |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/26/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 12/19/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/19/2024 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/17/2025 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/19/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 2/19/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 2/25/2025 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/25/2025 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/28/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/11/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 3/11/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/18/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/1/2025 | Approved | JOHN KIDWELL |
| Gas Test | 4/1/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 4/1/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/1/2025 | Approved | JOHN KIDWELL |
| Insulation | 4/9/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 4/23/2025 | Approved | JOHN KIDWELL |
| Final | 6/6/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 6/6/2025 | Approved | JOHN KIDWELL |
| Final | 6/11/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 6/11/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | JOHN KIDWELL |
| Final | 7/10/2025 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 7/10/2025 | Approved | JOHN KIDWELL |