9606 N SWINTON AVE 91343
Certificate Information: 9606 N SWINTON AVE 91343
- Application / Permit
- 24016-20000-35942
- Plan Check / Job No.
- B24VN22604
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT SECOND FLOOR REC ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). PER ENGINEER DESIGN.
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/18/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/22/2024 | APPLICANT |
| Applicant returned to address corrections | 1/21/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/24/2025 | ANGELICA MARTINEZ |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 2/19/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
| CofO Issued | 3/3/2026 | RUBEN SALAS |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Express Painting And Maintenance; Lic. No.: 981842-B | P O BOX 2910 LOS ANGELES, CA 90078 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/20/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/20/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/20/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 3/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 3/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Special/Order Compliance | 3/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 5/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 6/4/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/16/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 6/16/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/16/2025 | Approved | DAVID ANDERSON |
| Wood Frame | 6/16/2025 | Approved | DAVID ANDERSON |
| Insulation | 7/3/2025 | No Access for Inspection | MICHAEL CORTEZ |
| Shower Pan | 7/3/2025 | No Access for Inspection | MICHAEL CORTEZ |
| Insulation | 7/9/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/9/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/16/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/2/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 2/3/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 2/19/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |