4961 N WAWONA ST 90041

Certificate Information: 4961 N WAWONA ST 90041

Application / Permit
24016-20000-35452
Plan Check / Job No.
B24VN22131
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN EXISTING 20'-9"x 32'-0" UNPERMITTED STRUCTURE BUILT PRIOR TO JAN. 1, 2018 TO AN ACCESSORY DWELLING UNIT PER GCS 65852.23. EXISTING CONSTRUCTION THAT DOES NOT POSE A THREAT TO THE PUBLIC'S HEALTH AND SAFETY WAS ALLOWED PER GOVERNMENT CODE SECTION 55.852.2(d)(2).
Permit Issued
Issued on 1/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2024 APPLICANT
Assigned to Plan Check Engineer 11/13/2024 JESSE ARELLANO
Corrections Issued 11/14/2024 JESSE ARELLANO
Building Plans Picked Up 11/19/2024 APPLICANT
Applicant returned to address corrections 12/12/2024 ROSENDO MEDINA
Plan Check Approved 12/24/2024 GIOVANNY CHAVEZ
Issued 1/7/2025 APPLICANT
CofO in Progress 9/26/2025 DAVID WILLIAMS
Permit Finaled 9/28/2025 DEROLD HAUFF
CofO Issued 9/28/2025 DEROLD HAUFF
Permit Finaled 9/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/5/2024 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 12/10/2024 XOCHITL ARQUIETA
Grading Pre-Inspection Cleared 12/10/2024 MANUEL TEJADA
Miscellaneous Cleared 12/10/2024 XOCHITL ARQUIETA
Miscellaneous Cleared 12/10/2024 XOCHITL ARQUIETA
Sewer availability Cleared 12/10/2024 XOCHITL ARQUIETA
Hydrant and Access approval Cleared 12/20/2024 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/24/2025 Partial Approval BRENDAN MORELLI
Sewer 2/24/2025 Partial Approval BRENDAN MORELLI
Underground Mechanical 2/24/2025 Partial Approval BRENDAN MORELLI
Pre-Inspection 3/7/2025 Partial Inspection BRENDAN MORELLI
Footing/Foundation/Slab 3/14/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/27/2025 Approved DAVID WILLIAMS
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval JOSH MEISTER
Insulation 4/4/2025 Partial Approval JOSH MEISTER
Rough-Elec/Plmb/HVAC 4/14/2025 Partial Approval DAVID WILLIAMS
Insulation 4/21/2025 Approved REGINA MENDEZ
Shower Pan 4/21/2025 Approved REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 4/28/2025 Approved DAVID WILLIAMS
Drywall Nailing 5/2/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 5/12/2025 Approved REGINA MENDEZ
Sewer 6/24/2025 Approved DAVID WILLIAMS
Service/Power Release 7/10/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 9/12/2025 Approved DAVID WILLIAMS
Final 9/12/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 9/12/2025 Approved DAVID WILLIAMS
Green Building Rough 9/12/2025 Approved DAVID WILLIAMS
MERV13>=Final 9/12/2025 Approved DAVID WILLIAMS
MERV13>=Rough 9/12/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 9/12/2025 Approved DAVID WILLIAMS
Final 9/26/2025 OK to Issue CofO DAVID WILLIAMS