- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | JESSE ARELLANO |
| Corrections Issued | 11/14/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 11/19/2024 | APPLICANT |
| Applicant returned to address corrections | 12/12/2024 | ROSENDO MEDINA |
| Plan Check Approved | 12/24/2024 | GIOVANNY CHAVEZ |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 9/26/2025 | DAVID WILLIAMS |
| Permit Finaled | 9/28/2025 | DEROLD HAUFF |
| CofO Issued | 9/28/2025 | DEROLD HAUFF |
| Permit Finaled | 9/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2024 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2024 | XOCHITL ARQUIETA |
| Grading Pre-Inspection | Cleared | 12/10/2024 | MANUEL TEJADA |
| Miscellaneous | Cleared | 12/10/2024 | XOCHITL ARQUIETA |
| Miscellaneous | Cleared | 12/10/2024 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 12/10/2024 | XOCHITL ARQUIETA |
| Hydrant and Access approval | Cleared | 12/20/2024 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/24/2025 | Partial Approval | BRENDAN MORELLI |
| Sewer | 2/24/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 2/24/2025 | Partial Approval | BRENDAN MORELLI |
| Pre-Inspection | 3/7/2025 | Partial Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/14/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/27/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 4/3/2025 | Conditional Approval | JOSH MEISTER |
| Insulation | 4/4/2025 | Partial Approval | JOSH MEISTER |
| Rough-Elec/Plmb/HVAC | 4/14/2025 | Partial Approval | DAVID WILLIAMS |
| Insulation | 4/21/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 4/21/2025 | Approved | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/28/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 5/2/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/12/2025 | Approved | REGINA MENDEZ |
| Sewer | 6/24/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 7/10/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | DAVID WILLIAMS |
| Final | 9/12/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 9/12/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 9/12/2025 | Approved | DAVID WILLIAMS |
| MERV13>=Final | 9/12/2025 | Approved | DAVID WILLIAMS |
| MERV13>=Rough | 9/12/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 9/12/2025 | Approved | DAVID WILLIAMS |
| Final | 9/26/2025 | OK to Issue CofO | DAVID WILLIAMS |