9520-9522 N RHEA AVE 91324
Certificate Information: 9520-9522 N RHEA AVE 91324
- Application / Permit
- 24016-20000-35317
- Plan Check / Job No.
- B24VN22011
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 66333 ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/3/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/9/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/15/2024 | APPLICANT |
| Applicant returned to address corrections | 4/11/2025 | PINANK PATEL |
| Applicant returned to address corrections | 4/15/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/15/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/3/2025 | APPLICANT |
| CofO in Progress | 9/10/2025 | DAVID SCANTLIN |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
| CofO Issued | 4/4/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/12/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | RYAN CASTRO |
Contact Information
| Contractor | Z Enterprise Inc; Lic. No.: 1095386-B | 3633 JADE COURT WEST COVINA, CA 91792 |
| Engineer | Wong,, George Voon; Lic. No.: C49894 | 253 BARBADOS DR WALNUT, CA 91789 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/12/2025 | Conditional Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 6/13/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 7/7/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 7/7/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 7/7/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/23/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 7/23/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/23/2025 | Partial Approval | KRISTEN CAUSEY |
| Deputy Wood Construction | 7/24/2025 | Conditional Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/4/2025 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Approved | KRISTEN CAUSEY |
| Insulation | 8/4/2025 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 8/11/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 8/11/2025 | Approved | KRISTEN CAUSEY |
| Final | 9/2/2025 | Corrections Issued | KRISTEN CAUSEY |
| Green Building Final | 9/2/2025 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | KRISTEN CAUSEY |
| Smoke Detectors | 9/2/2025 | Approved | KRISTEN CAUSEY |
| Final | 9/9/2025 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 1/26/2026 | Approved | DAVID SCANTLIN |