7944-7946 N FAIRCHILD AVE 91306

Certificate Information: 7944-7946 N FAIRCHILD AVE 91306

Application / Permit
24016-20000-35280
Plan Check / Job No.
B24VN21970
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 12/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2024 APPLICANT
Assigned to Plan Check Engineer 11/12/2024 ARTIN ZARUKIAN
Corrections Issued 11/12/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/19/2024 APPLICANT
Plan Check Approved 12/16/2024 KAMYAR EMAMI
Issued 12/20/2024 APPLICANT
CofO in Progress 7/23/2025 ALEXANDER HANDY
Permit Finaled 8/26/2025 JOHN JANSON
CofO Issued 8/26/2025 JOHN JANSON
Permit Finaled 8/26/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/16/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/16/2024 CARLOS AGUILERA
Sewer availability Cleared 12/16/2024 CARLOS AGUILERA

Contact Information

Contractor Yor Construction And Investments Inc; Lic. No.: 978430-B 12135 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2025 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 3/4/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 3/5/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 3/5/2025 Not Ready for Inspection SCOTT SOBEL
Special/Order Compliance 3/5/2025 Corrections Issued SCOTT SOBEL
Footing/Foundation/Slab 3/11/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 3/11/2025 Partial Approval SCOTT SOBEL
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval SCOTT SOBEL
Footing/Foundation/Slab 4/1/2025 Not Ready for Inspection SCOTT SOBEL
Deputy Drilled-In Anchors 4/7/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 4/7/2025 Approved SCOTT SOBEL
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 4/24/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 4/24/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 5/5/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 5/5/2025 Not Ready for Inspection ALEXANDER HANDY
Insulation 5/5/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Approved ALEXANDER HANDY
Shower Pan 5/13/2025 Approved ALEXANDER HANDY
Drywall Nailing 5/23/2025 Approved ARUTYUN MADATYAN
Green Building Rough 5/23/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/28/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/16/2025 Approved ALEXANDER HANDY
Final 7/16/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 7/16/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV No Gas ALEXANDER HANDY
Smoke Detectors 7/16/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 7/22/2025 Approved ALEXANDER HANDY
Final 7/22/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 7/22/2025 Approved ALEXANDER HANDY
HVAC-Final 7/22/2025 Approved ALEXANDER HANDY
PLUMBING-Final 7/22/2025 Approved ALEXANDER HANDY
Service/Power Release 7/22/2025 Approved ALEXANDER HANDY