7944-7946 N FAIRCHILD AVE 91306
Certificate Information: 7944-7946 N FAIRCHILD AVE 91306
- Application / Permit
- 24016-20000-35280
- Plan Check / Job No.
- B24VN21970
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/12/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/19/2024 | APPLICANT |
| Plan Check Approved | 12/16/2024 | KAMYAR EMAMI |
| Issued | 12/20/2024 | APPLICANT |
| CofO in Progress | 7/23/2025 | ALEXANDER HANDY |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
| CofO Issued | 8/26/2025 | JOHN JANSON |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/16/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Yor Construction And Investments Inc; Lic. No.: 978430-B | 12135 MIRANDA ST VALLEY VILLAGE, CA 91607 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2025 | Approved | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/5/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 3/5/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Special/Order Compliance | 3/5/2025 | Corrections Issued | SCOTT SOBEL |
| Footing/Foundation/Slab | 3/11/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 3/11/2025 | Partial Approval | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 4/1/2025 | Conditional Approval | SCOTT SOBEL |
| Footing/Foundation/Slab | 4/1/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 4/7/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 4/7/2025 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 4/24/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/24/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 4/24/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/5/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 5/5/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 5/13/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/23/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/23/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | ALEXANDER HANDY |
| Final | 7/16/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 7/16/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Smoke Detectors | 7/16/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/22/2025 | Approved | ALEXANDER HANDY |
| Final | 7/22/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 7/22/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 7/22/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 7/22/2025 | Approved | ALEXANDER HANDY |
| Service/Power Release | 7/22/2025 | Approved | ALEXANDER HANDY |