10941 N SCOVILLE AVE 91040
Certificate Information: 10941 N SCOVILLE AVE 91040
- Application / Permit
- 24016-20000-34844
- Plan Check / Job No.
- B24VN21569
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | JESSE ARELLANO |
| Corrections Issued | 11/9/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 11/12/2024 | APPLICANT |
| Issued | 11/15/2024 | APPLICANT |
| CofO in Progress | 3/13/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
| CofO Issued | 4/16/2026 | RUBEN SALAS |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 11/15/2024 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/5/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/20/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 3/20/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 3/20/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | WILLIAM WREN |
| Sewer | 4/3/2025 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 4/3/2025 | Approved | WILLIAM WREN |
| Sewer | 4/9/2025 | Approved | WILLIAM WREN |
| Shower Pan | 4/9/2025 | Approved | WILLIAM WREN |
| Insulation | 4/17/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/23/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 6/4/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/8/2025 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 7/8/2025 | Corrections Issued | DAVID MATSON |
| Green Building Final | 7/8/2025 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 7/8/2025 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 7/8/2025 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Final | 10/28/2025 | Corrections Issued | JAVIER RAMOS JR |
| Smoke Detectors | 10/28/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 3/2/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 3/2/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Rough | 3/2/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Final | 3/12/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 3/12/2026 | Approved | NICHOLAS TROWBRIDGE |