10941 N SCOVILLE AVE 91040

Certificate Information: 10941 N SCOVILLE AVE 91040

Application / Permit
24016-20000-34844
Plan Check / Job No.
B24VN21569
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
Permit Issued
Issued on 11/15/2024
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 JESSE ARELLANO
Corrections Issued 11/9/2024 JESSE ARELLANO
Building Plans Picked Up 11/12/2024 APPLICANT
Issued 11/15/2024 APPLICANT
CofO in Progress 3/13/2026 NICHOLAS TROWBRIDGE
Permit Finaled 4/16/2026 RUBEN SALAS
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/13/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/13/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/13/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 11/15/2024 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2025 Approved WILLIAM WREN
PLUMBING-Rough 2/5/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/20/2025 Approved WILLIAM WREN
HVAC-Rough 3/20/2025 Approved WILLIAM WREN
PLUMBING-Rough 3/20/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 4/1/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval WILLIAM WREN
Sewer 4/3/2025 Partial Approval WILLIAM WREN
Underground Mechanical 4/3/2025 Approved WILLIAM WREN
Sewer 4/9/2025 Approved WILLIAM WREN
Shower Pan 4/9/2025 Approved WILLIAM WREN
Insulation 4/17/2025 Approved WILLIAM WREN
Drywall Nailing 4/23/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 5/15/2025 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 6/4/2025 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/8/2025 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 7/8/2025 Corrections Issued DAVID MATSON
Green Building Final 7/8/2025 Not Ready for Inspection DAVID MATSON
Green Building Rough 7/8/2025 Not Ready for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Not Ready DAVID MATSON
Smoke Detectors 7/8/2025 Corrections Issued DAVID MATSON
ELECTRICAL-Final 10/28/2025 Corrections Issued JAVIER RAMOS JR
Smoke Detectors 10/28/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/2/2026 Approved NICHOLAS TROWBRIDGE
Final 3/2/2026 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 3/2/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 3/2/2026 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Final 3/12/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 3/12/2026 Approved NICHOLAS TROWBRIDGE