6943-6945 N ZELZAH AVE 91335
Certificate Information: 6943-6945 N ZELZAH AVE 91335
- Application / Permit
- 24016-20000-34797
- Plan Check / Job No.
- B24VN21530
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/7/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/13/2024 | APPLICANT |
| Applicant returned to address corrections | 1/17/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/27/2025 | MADISON ODELL |
| Plan Check Approved | 2/14/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 11/4/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 11/7/2025 | JOHN JANSON |
| CofO Issued | 11/7/2025 | JOHN JANSON |
| Permit Finaled | 11/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/15/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 4/11/2025 | Partial Inspection | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 4/17/2025 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 4/17/2025 | Partial Approval | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/22/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/25/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/5/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/15/2025 | Corrections Issued | JUAN ALVARADO |
| BUILDING-Rough-Frame | 5/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/19/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/19/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/27/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/27/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 5/27/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/27/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 6/2/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/13/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 7/22/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/27/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 10/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 10/27/2025 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 10/27/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 11/3/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | ARUTYUN MADATYAN |