6943-6945 N ZELZAH AVE 91335

Certificate Information: 6943-6945 N ZELZAH AVE 91335

Application / Permit
24016-20000-34797
Plan Check / Job No.
B24VN21530
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 2/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 11/6/2024 ARTIN ZARUKIAN
Corrections Issued 11/7/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/13/2024 APPLICANT
Applicant returned to address corrections 1/17/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 1/27/2025 MADISON ODELL
Plan Check Approved 2/14/2025 ARAMIK SHAHMIRZAIAN
Issued 2/18/2025 APPLICANT
CofO in Progress 11/4/2025 ARUTYUN MADATYAN
Permit Finaled 11/7/2025 JOHN JANSON
CofO Issued 11/7/2025 JOHN JANSON
Permit Finaled 11/7/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/15/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/15/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/26/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 4/11/2025 Partial Inspection KRISTEN CAUSEY
Deputy Drilled-In Anchors 4/17/2025 Conditional Approval ROBERT GOLD
PLUMBING-Rough 4/17/2025 Partial Approval JUAN ALVARADO
Footing/Foundation/Slab 4/22/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 4/25/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 5/5/2025 Partial Approval ARUTYUN MADATYAN
Sewer 5/5/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 5/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 5/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/15/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 5/19/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 5/19/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 5/19/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/27/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 5/27/2025 Approved ARUTYUN MADATYAN
Green Building Rough 5/27/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 5/27/2025 Approved ARUTYUN MADATYAN
Insulation 5/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 5/27/2025 Partial Approval ARUTYUN MADATYAN
Insulation 6/2/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 6/13/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Approved ARUTYUN MADATYAN
Shower Pan 7/22/2025 Approved ARUTYUN MADATYAN
Final 10/27/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 10/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 10/27/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 10/27/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 11/3/2025 Approved ARUTYUN MADATYAN
Final 11/3/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 11/3/2025 Approved ARUTYUN MADATYAN
HVAC-Final 11/3/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 11/3/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved ARUTYUN MADATYAN