19341 W VANOWEN ST 91335
Certificate Information: 19341 W VANOWEN ST 91335
- Application / Permit
- 24016-20000-34746
- Plan Check / Job No.
- B24VN21477
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO A NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 11/5/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/2/2025 | MADISON ODELL |
| Applicant returned to address corrections | 1/18/2025 | MADISON ODELL |
| Applicant returned to address corrections | 1/30/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/18/2025 | MOHAMMAD ESMAILI |
| Issued | 2/19/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | JUAN ALVARADO |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
| CofO Issued | 3/17/2026 | JOHN JANSON |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2024 | EDGAR ALCARAZ |
| ZI | Cleared | 1/25/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 2/27/2025 | Corrections Issued | JUAN ALVARADO |
| PLUMBING-Rough | 2/27/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 3/14/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/3/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/8/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Rough | 4/18/2025 | Corrections Issued | ROBERT GOLD |
| Interior/Exterior Lathing | 4/23/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/25/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 4/25/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 4/25/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | JUAN ALVARADO |
| Gas Test | 4/30/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 4/30/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 4/30/2025 | Approved | JUAN ALVARADO |
| Insulation | 5/5/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 5/9/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 8/14/2025 | Partial Approval | JUAN ALVARADO |
| Final | 11/10/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 11/10/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 11/10/2025 | Approved | JUAN ALVARADO |
| Final | 11/24/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 2/4/2026 | Corrections Issued | JUAN ALVARADO |
| Final | 3/9/2026 | No Access for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/12/2026 | Approved | JUAN ALVARADO |
| Final | 3/12/2026 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 3/12/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 3/12/2026 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 3/16/2026 | Approved | JUAN ALVARADO |