19341 W VANOWEN ST 91335

Certificate Information: 19341 W VANOWEN ST 91335

Application / Permit
24016-20000-34746
Plan Check / Job No.
B24VN21477
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO A NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 11/4/2024 MIROOSH KHACHATOORIAN
Corrections Issued 11/5/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/2/2025 MADISON ODELL
Applicant returned to address corrections 1/18/2025 MADISON ODELL
Applicant returned to address corrections 1/30/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/18/2025 MOHAMMAD ESMAILI
Issued 2/19/2025 APPLICANT
CofO in Progress 3/13/2026 JUAN ALVARADO
Permit Finaled 3/17/2026 JOHN JANSON
CofO Issued 3/17/2026 JOHN JANSON
Permit Finaled 3/17/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/18/2024 EDGAR ALCARAZ
ZI Cleared 1/25/2025 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2025 Conditional Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 2/24/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 2/27/2025 Corrections Issued JUAN ALVARADO
PLUMBING-Rough 2/27/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 3/14/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 4/3/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/8/2025 Partial Approval JUAN ALVARADO
Interior/Exterior Lathing 4/8/2025 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 4/18/2025 Corrections Issued ROBERT GOLD
Interior/Exterior Lathing 4/23/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 4/25/2025 No Access for Inspection ARUTYUN MADATYAN
Green Building Rough 4/25/2025 No Access for Inspection ARUTYUN MADATYAN
HVAC-Rough 4/25/2025 No Access for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/30/2025 Approved JUAN ALVARADO
Gas Test 4/30/2025 Approved JUAN ALVARADO
Green Building Rough 4/30/2025 Approved JUAN ALVARADO
HVAC-Rough 4/30/2025 Approved JUAN ALVARADO
Insulation 5/5/2025 Approved JUAN ALVARADO
Drywall Nailing 5/9/2025 Approved JUAN ALVARADO
Shower Pan 8/14/2025 Partial Approval JUAN ALVARADO
Final 11/10/2025 Corrections Issued JUAN ALVARADO
Green Building Final 11/10/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 11/10/2025 Approved JUAN ALVARADO
Final 11/24/2025 Corrections Issued JUAN ALVARADO
Final 2/4/2026 Corrections Issued JUAN ALVARADO
Final 3/9/2026 No Access for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 3/12/2026 Approved JUAN ALVARADO
Final 3/12/2026 OK to Issue CofO JUAN ALVARADO
HVAC-Final 3/12/2026 Approved JUAN ALVARADO
PLUMBING-Final 3/12/2026 Approved JUAN ALVARADO
Footing/Foundation/Slab 3/16/2026 Approved JUAN ALVARADO