15055 W OXNARD ST 91411
Certificate Information: 15055 W OXNARD ST 91411
- Application / Permit
- 24016-20000-34650
- Plan Check / Job No.
- B24VN21387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ePlan: TENANT IMPROVEMENT TO (E) OFFICE AND WAREHOUSE
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/22/2025
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Zoning Architect | 11/7/2024 | AMIR NAKHLA |
| Assigned to Plan Check Engineer | 11/14/2024 | DANIEL YIP |
| Corrections Issued | 11/20/2024 | DANIEL YIP |
| Quality Review Completed | 11/21/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/24/2025 | DANIEL YIP |
| Applicant returned to address corrections | 2/14/2025 | DANIEL YIP |
| Applicant returned to address corrections | 3/12/2025 | DANIEL YIP |
| Plan Check Approved | 3/21/2025 | DANIEL YIP |
| Issued | 3/21/2025 | APPLICANT |
| Permit Finaled | 5/21/2025 | BRIAN KELLY |
Permit Application Clearance Information
| Green Code | Cleared | 1/16/2025 | MICHAEL AYERS |
| Zoning Plan Check | Cleared | 1/22/2025 | Gurunath Nesarajah |
| DAS Clearance | Cleared | 2/3/2025 | Gurunath Nesarajah |
| Metro Rail approval | Cleared | 3/19/2025 | JENNIFER SU |
Contact Information
| Architect | Lindholm,, Christopher D; Lic. No.: C32504 | 17496 STAR CANYON COURT RIVERSIDE, CA 92503 |
| Contractor | Uprite Construction Corporation; Lic. No.: 932018-B | , |
| Engineer | Nam,, Young Keun; Lic. No.: S4029 | 2151 MICHELSON DR. SUITE 240 IRVINE, CA 92612 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/24/2025 | Partial Approval | BRIAN KELLY |
| Insulation | 3/25/2025 | Approved | BRIAN KELLY |
| Drywall Nailing | 3/26/2025 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 3/27/2025 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 3/28/2025 | Approved | BRIAN KELLY |
| Footing/Foundation/Slab | 4/11/2025 | Partial Inspection | BRIAN KELLY |
| Deputy Other (see comments) | 4/14/2025 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 4/29/2025 | Conditional Approval | BRIAN KELLY |
| Final | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| METHANE-Final | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| METHANE-Rough | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 5/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/14/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 5/14/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 5/14/2025 | Approved | BRIAN KELLY |
| METHANE-Final | 5/14/2025 | Approved | BRIAN KELLY |
| METHANE-Rough | 5/14/2025 | Approved | BRIAN KELLY |
| Reinforced Masonry Frame | 5/14/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 5/14/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/21/2025 | Permit Finaled | BRIAN KELLY |
| Green Building Final | 5/21/2025 | Approved | BRIAN KELLY |
| Reinforced Masonry Frame | 5/21/2025 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 5/21/2025 | Approved | BRIAN KELLY |