7528-7530 N SECURITY AVE 91504

Certificate Information: 7528-7530 N SECURITY AVE 91504

Application / Permit
24016-20000-34378
Plan Check / Job No.
B24VN21133
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 11/26/2024
Issuing Office
Valley
Current Status
Issued on 11/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/4/2024 JEROME MAGAT PALMA
Corrections Issued 11/5/2024 JEROME MAGAT PALMA
Building Plans Picked Up 11/7/2024 APPLICANT
Applicant returned to address corrections 11/22/2024 HAYATO TSUCHIYA
Plan Check Approved 11/26/2024 PINANK PATEL
Issued 11/26/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/15/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/15/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/18/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2024 Corrections Issued DAVID ANDERSON
Deputy Drilled-In Anchors 12/10/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/13/2024 Approved DAVID ANDERSON
PLUMBING-Rough 12/13/2024 Approved DAVID ANDERSON
Sewer 12/13/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/27/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 12/27/2024 Corrections Issued ARAM AVEDISIAN
Green Building Rough 12/27/2024 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Rough 12/27/2024 Not Ready for Inspection ARAM AVEDISIAN
Special/Order Compliance 12/27/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 1/3/2025 Not Ready for Inspection DAVID ANDERSON
Wood Frame 1/3/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 1/22/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 1/22/2025 Approved DAVID ANDERSON
Green Building Rough 1/22/2025 Approved DAVID ANDERSON
HVAC-Rough 1/22/2025 Approved DAVID ANDERSON
MERV13>=Rough 1/22/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/31/2025 Partial Approval DAVID ANDERSON
Insulation 2/5/2025 Approved DAVID ANDERSON
Shower Pan 2/5/2025 Approved DAVID ANDERSON
Drywall Nailing 2/7/2025 Approved DAVID ANDERSON