7719 N VANALDEN AVE 91335

Certificate Information: 7719 N VANALDEN AVE 91335

Application / Permit
24016-20000-34282
Plan Check / Job No.
B24VN21063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing detached garage, recreation room and storage into new detached ADU per GC 66323(a)(1)
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 SUNMIN LEE
Corrections Issued 11/4/2024 SUNMIN LEE
Applicant returned to address corrections 4/9/2025 JOHN MESIAS
Applicant returned to address corrections 5/16/2025 ADAM HEGAZI
Plan Check Approved 5/21/2025 ADAM HEGAZI
Issued 5/30/2025 APPLICANT
CofO in Progress 3/2/2026 ARUTYUN MADATYAN
Permit Finaled 3/10/2026 JOHN JANSON
CofO Issued 3/10/2026 JOHN JANSON
Permit Finaled 3/10/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/16/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/16/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/17/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803
Engineer Garcia,, Francisco Javier; Lic. No.: NA76510       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/17/2025 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 10/17/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/17/2025 Partial Approval ARUTYUN MADATYAN
Sewer 10/17/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 11/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 11/14/2025 Corrections Issued ARUTYUN MADATYAN
Insulation 11/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 11/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 11/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/18/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 11/18/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 11/18/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 11/18/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 11/18/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 11/21/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 11/21/2025 Approved ARUTYUN MADATYAN
Insulation 11/21/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 11/21/2025 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 12/2/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/18/2026 OK to Expire Permit ARUTYUN MADATYAN
Final 2/18/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 2/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 2/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 2/18/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 2/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 2/18/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/27/2026 Approved ARUTYUN MADATYAN
Final 2/27/2026 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 2/27/2026 Approved ARUTYUN MADATYAN
HVAC-Final 2/27/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/27/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 2/27/2026 Approved ARUTYUN MADATYAN