7719 N VANALDEN AVE 91335
Certificate Information: 7719 N VANALDEN AVE 91335
- Application / Permit
- 24016-20000-34282
- Plan Check / Job No.
- B24VN21063
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing detached garage, recreation room and storage into new detached ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Current Status
- CofO Issued on 3/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | SUNMIN LEE |
| Corrections Issued | 11/4/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 4/9/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 5/16/2025 | ADAM HEGAZI |
| Plan Check Approved | 5/21/2025 | ADAM HEGAZI |
| Issued | 5/30/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 3/10/2026 | JOHN JANSON |
| CofO Issued | 3/10/2026 | JOHN JANSON |
| Permit Finaled | 3/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/16/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: NA76510 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/17/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 10/17/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 11/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Insulation | 11/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/18/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Rough | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 11/18/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/21/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 11/21/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 11/21/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 12/2/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/18/2026 | OK to Expire Permit | ARUTYUN MADATYAN |
| Final | 2/18/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 2/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 2/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/18/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 2/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 2/18/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/27/2026 | Approved | ARUTYUN MADATYAN |
| Final | 2/27/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 2/27/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 2/27/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/27/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 2/27/2026 | Approved | ARUTYUN MADATYAN |