6339 N MURIETTA AVE 91401
Certificate Information: 6339 N MURIETTA AVE 91401
- Application / Permit
- 24016-20000-34271
- Plan Check / Job No.
- B24VN21047
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). All work per engineering
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Current Status
- CofO Issued on 6/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | ISIS ARGUETA |
| Corrections Issued | 11/1/2024 | ISIS ARGUETA |
| Building Plans Picked Up | 11/4/2024 | APPLICANT |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 5/22/2025 | RYAN SALAZAR |
| CofO Issued | 6/13/2025 | RUBEN SALAS |
| Permit Finaled | 6/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/5/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 1/8/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Master In Design Inc; Lic. No.: 979219-B | 6011 RESEDA BLVD #1 TARZANA, CA 91356 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/6/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/12/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/12/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/24/2025 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/24/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 3/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 3/24/2025 | Corrections Issued | RYAN SALAZAR |
| Insulation | 3/28/2025 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/28/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/28/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/2/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 4/2/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/8/2025 | Approved | RYAN SALAZAR |
| Final | 5/8/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 5/8/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/8/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/8/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/8/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 5/8/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/8/2025 | Approved | RYAN SALAZAR |
| Final | 5/23/2025 | OK to Issue CofO | RYAN SALAZAR |