6339 N MURIETTA AVE 91401

Certificate Information: 6339 N MURIETTA AVE 91401

Application / Permit
24016-20000-34271
Plan Check / Job No.
B24VN21047
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). All work per engineering
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 6/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 ISIS ARGUETA
Corrections Issued 11/1/2024 ISIS ARGUETA
Building Plans Picked Up 11/4/2024 APPLICANT
Issued 1/23/2025 APPLICANT
CofO in Progress 5/22/2025 RYAN SALAZAR
CofO Issued 6/13/2025 RUBEN SALAS
Permit Finaled 6/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/5/2024 RYAN CASTRO
Sewer availability Cleared 11/5/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/12/2024 RYAN CASTRO
Construction near power lines Cleared 1/8/2025 RIDWAN HARDY
Construction within easement Cleared 1/8/2025 RIDWAN HARDY

Contact Information

Contractor Master In Design Inc; Lic. No.: 979219-B 6011 RESEDA BLVD #1      TARZANA, CA 91356
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/6/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 3/12/2025 Approved RYAN SALAZAR
Underground Mechanical 3/12/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 3/24/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 3/24/2025 Approved RYAN SALAZAR
Green Building Rough 3/24/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 3/24/2025 Corrections Issued RYAN SALAZAR
Insulation 3/28/2025 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 3/28/2025 Approved RYAN SALAZAR
PLUMBING-Rough 3/28/2025 Approved RYAN SALAZAR
Drywall Nailing 4/2/2025 Approved JAVIER RAMOS JR
Insulation 4/2/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/8/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 5/8/2025 Approved RYAN SALAZAR
Final 5/8/2025 Corrections Issued RYAN SALAZAR
Green Building Final 5/8/2025 Approved RYAN SALAZAR
Green Building Rough 5/8/2025 Approved RYAN SALAZAR
HVAC-Rough 5/8/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/8/2025 Approved RYAN SALAZAR
PLUMBING-Final 5/8/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/8/2025 Approved RYAN SALAZAR
Final 5/23/2025 OK to Issue CofO RYAN SALAZAR