7948-7948 1/2 N AURA AVE 91335
Certificate Information: 7948-7948 1/2 N AURA AVE 91335
- Application / Permit
- 24016-20000-34264
- Plan Check / Job No.
- B24VN21040
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATTACHED GARAGE & PORTION OF EX DWELLING INTO JR ACCESSORY DWELLING UNIT (JR ADU) PER GCS 65852.2(e)(1)(A) & 65852.22. RAISE ROOF OVER JR ADU WITH GABLE ROOF FRAMING.
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 11/2/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/12/2024 | APPLICANT |
| Plan Check Approved | 12/19/2024 | YAQUB MIRZA |
| Issued | 1/29/2025 | APPLICANT |
| CofO in Progress | 8/27/2025 | JUAN ALVARADO |
| Permit Finaled | 10/6/2025 | JOHN JANSON |
| CofO Issued | 10/6/2025 | JOHN JANSON |
| Permit Finaled | 10/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Belair Design & Development Inc; Lic. No.: 1102116-B | 8520 W PICO BLVD LOS ANGELES, CA 90035 |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/5/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Sewer | 2/18/2025 | Approved | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 3/5/2025 | Corrections Issued | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 3/11/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 3/12/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | JUAN ALVARADO |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/7/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 4/7/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 4/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Wood Frame | 4/15/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/17/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 4/22/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 4/22/2025 | Approved | JUAN ALVARADO |
| Insulation | 4/23/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 4/28/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/28/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Shower Pan | 4/28/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Drywall Nailing | 5/2/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 5/2/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 5/2/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 5/6/2025 | Approved | JUAN ALVARADO |
| Final | 7/14/2025 | Corrections Issued | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 7/14/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 7/24/2025 | Approved | JUAN ALVARADO |
| Final | 8/18/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 8/26/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 8/26/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 8/26/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 8/26/2025 | Approved | JUAN ALVARADO |