1577 W OAK GROVE DR 90041

Certificate Information: 1577 W OAK GROVE DR 90041

Application / Permit
24016-20000-34182
Plan Check / Job No.
B24VN20945
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A).
Permit Issued
Issued on 12/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/30/2024 JEROME MAGAT PALMA
Corrections Issued 10/30/2024 JEROME MAGAT PALMA
Building Plans Picked Up 11/6/2024 APPLICANT
Applicant returned to address corrections 12/4/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 12/6/2024 GIOVANNY CHAVEZ
Issued 12/6/2024 APPLICANT
CofO in Progress 6/6/2025 DAVID WILLIAMS
Permit Finaled 6/8/2025 DEROLD HAUFF
CofO Issued 6/8/2025 DEROLD HAUFF
Permit Finaled 6/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/21/2024 TREVOR QUAN
Sewer availability Cleared 11/21/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/27/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 1015 VISTA GRANDE ST      BURBANK, CA 91501

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2025 Conditional Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 1/10/2025 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 1/14/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 1/21/2025 Partial Approval CRAIG DAVIS
Deputy Drilled-In Anchors 1/22/2025 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 3/21/2025 Approved DAVID WILLIAMS
HVAC-Rough 3/21/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 3/24/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/24/2025 Approved LILIANA PORTILLO
Shower Pan 3/24/2025 Approved LILIANA PORTILLO
Underground Mechanical 3/24/2025 Partial Approval LILIANA PORTILLO
Underground Mechanical 3/26/2025 Approved DAVID WILLIAMS
Wood Frame 3/26/2025 Approved DAVID WILLIAMS
Insulation 4/1/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 4/1/2025 Approved REGINA MENDEZ
Drywall Nailing 4/7/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 5/28/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 5/28/2025 Approved DAVID WILLIAMS
Final 5/28/2025 Corrections Issued DAVID WILLIAMS
Gas Test 5/28/2025 Approved DAVID WILLIAMS
Green Building Final 5/28/2025 Approved DAVID WILLIAMS
Green Building Rough 5/28/2025 Approved DAVID WILLIAMS
HVAC-Final 5/28/2025 Approved DAVID WILLIAMS
PLUMBING-Final 5/28/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Required DAVID WILLIAMS
Smoke Detectors 5/28/2025 Approved DAVID WILLIAMS
Final 6/6/2025 OK to Issue CofO DAVID WILLIAMS