545 N SPOLETO DR 90272

Certificate Information: 545 N SPOLETO DR 90272

Application / Permit
24016-20000-34171
Plan Check / Job No.
B24VN20937
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior/Interior Remodel to (E) SFD . Interior Remodel including Kitchen/Bathroom remodels, and reconfigure interior partitions and floor plan layout, and new vaulted ceiling area . Exterior Remodel including new skylight, and alter exterior window/door opening sizes and locations .
Permit Issued
Issued on 12/13/2024
Issuing Office
Metro
Current Status
Permit Finaled on 1/20/2026

Permit Application Status History

Submitted 10/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 KAMYAR EMAMI
Corrections Issued 10/31/2024 KAMYAR EMAMI
Building Plans Picked Up 11/4/2024 APPLICANT
Plan Check Approved 11/22/2024 ISIS ARGUETA
Plan Check Approved 11/22/2024 GEORGE ALVAREZ
Issued 12/13/2024 APPLICANT
Permit Finaled 1/20/2026 HERBERT GIRON

Permit Application Clearance Information

Sewer availability Cleared 11/10/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 11/21/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 11/21/2024 VASIL MIHALEV

Contact Information

Contractor Rivera Home Builders; Lic. No.: 1080029-B 14913 BAYOU AVE      BELLFLOWER, CA 90706
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2025 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 7/8/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 7/8/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 7/8/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 7/10/2025 Approved HERBERT GIRON
HVAC-Rough 7/10/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 7/10/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 7/18/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 8/1/2025 Corrections Issued HERBERT GIRON
Green Building Rough 8/1/2025 Approved HERBERT GIRON
HVAC-Rough 8/1/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/5/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Corrections Issued HERBERT GIRON
Insulation 8/7/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/13/2025 Approved HERBERT GIRON
Drywall Nailing 8/13/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved HERBERT GIRON
Shower Pan 8/13/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 8/19/2025 Partial Approval HERBERT GIRON
Shower Pan 8/19/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 9/23/2025 Approved HERBERT GIRON
Gas Test 10/31/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Not Ready HERBERT GIRON
Final 1/12/2026 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/12/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/15/2026 Approved HERBERT GIRON
Final 1/15/2026 Corrections Issued HERBERT GIRON
HVAC-Final 1/15/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/15/2026 Approved HERBERT GIRON
Smoke Detectors 1/15/2026 Approved HERBERT GIRON
Final 1/20/2026 Permit Finaled HERBERT GIRON
HVAC-Final 1/20/2026 Approved HERBERT GIRON