20538 W KESWICK ST 91306
Certificate Information: 20538 W KESWICK ST 91306
- Application / Permit
- 24016-20000-34165
- Plan Check / Job No.
- B24VN20927
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO (N) 561 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/1/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/7/2024 | APPLICANT |
| Issued | 1/15/2025 | APPLICANT |
| CofO in Progress | 9/9/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
| CofO Issued | 2/20/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/7/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 1/14/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/14/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2025 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 3/10/2025 | Corrections Issued | SCOTT SOBEL |
| Underground Mechanical | 3/10/2025 | Conditional Approval | SCOTT SOBEL |
| Footing/Foundation/Slab | 3/21/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | SCOTT SOBEL |
| Footing/Foundation/Slab | 4/4/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 4/30/2025 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 4/30/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/7/2025 | Conditional Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 5/7/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 5/7/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 5/7/2025 | Approved | ALEXANDER HANDY |
| Sewer | 5/7/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 5/7/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/15/2025 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 5/15/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | ALEXANDER HANDY |
| Insulation | 5/22/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/26/2025 | Approved | ALEXANDER HANDY |
| Final | 8/26/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 8/26/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 8/26/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 8/26/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| Final | 9/8/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 9/8/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Approved | ALEXANDER HANDY |