5033 S COMPTON AVE 90011
Certificate Information: 5033 S COMPTON AVE 90011
- Application / Permit
- 24016-20000-34162
- Plan Check / Job No.
- B24VN20920
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePlan. change of use from Barber Shop to restaurant, accessibility and remove existing parking spaces.
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 11/14/2024 | CALEB WONG |
| Corrections Issued | 11/16/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 11/20/2024 | PETER KIM |
| Applicant returned to address corrections | 12/2/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/16/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/20/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/26/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/9/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/14/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/21/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 1/31/2025 | SALVADOR QUINTANILLA |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | ALFREDO LOPEZ |
| Permit Finaled | 3/2/2026 | ERNESTO CORRAL |
| CofO Issued | 3/2/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/2/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 12/10/2024 | ANACANY HURTADO |
| Food establishment approval | Cleared | 12/16/2024 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 12/17/2024 | BOGDAN SERBANESCU |
| Community Plan Implem. Overlay | Cleared | 12/26/2024 | ANACANY HURTADO |
| DAS Clearance | Cleared | 1/7/2025 | Fernando Flores |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 1/8/2025 | CHRISTINA BRACO |
| Historic Resource Verification | Cleared | 1/23/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 1/23/2025 | YASMINE BASHIRI |
| Zoning Plan Check | Cleared | 1/30/2025 | CALEB WONG |
Contact Information
| Contractor | D R Construction; Lic. No.: 826773-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/18/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 3/20/2025 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 3/25/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 2/20/2026 | OK to Issue CofO | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 2/20/2026 | Approved | ALFREDO LOPEZ |