10125-10127 N COLUMBUS AVE 91345

Certificate Information: 10125-10127 N COLUMBUS AVE 91345

Application / Permit
24016-20000-34126
Plan Check / Job No.
B24VN20902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO AN A.D.U. PER STATE LAW
Permit Issued
Issued on 12/28/2024
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 LUKE GONZALES
Corrections Issued 11/4/2024 LUKE GONZALES
Plan Check Approved 12/27/2024 JOSEPH RAFOLS
Issued 12/28/2024 APPLICANT
CofO in Progress 8/14/2025 JENNIFER RABUCHIN
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/5/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/7/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 2/24/2025 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 2/24/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/3/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/21/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/21/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/30/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/30/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/30/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/4/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/6/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/6/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Approved JENNIFER RABUCHIN
Green Building Rough 6/6/2025 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 6/6/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/6/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 6/13/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/13/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 7/24/2025 Approved JENNIFER RABUCHIN
Final 7/24/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/24/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 7/24/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/24/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/24/2025 Approved JENNIFER RABUCHIN
Final 7/30/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 8/14/2025 Approved JENNIFER RABUCHIN
Final 8/14/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/14/2025 Approved JENNIFER RABUCHIN
HVAC-Final 8/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/14/2025 Approved JENNIFER RABUCHIN