16034-16038 W LIGGETT ST 91343
Certificate Information: 16034-16038 W LIGGETT ST 91343
- Application / Permit
- 24016-20000-34041
- Plan Check / Job No.
- B24VN20815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 2ND FLR PORTION OF SFD TO ACCESSORY DWELLING UNIT (535 SQ FT) PER LAMC 12.22 A.33(c) and (e). CONVERT ATTACHED GARAGE & PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT (487 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Current Status
- CofO Issued on 7/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/2/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/4/2024 | APPLICANT |
| Plan Check Approved | 3/14/2025 | ANGELICA MARTINEZ |
| Issued | 3/14/2025 | APPLICANT |
| CofO in Progress | 7/1/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 7/2/2026 | RUBEN SALAS |
| CofO Issued | 7/2/2026 | RUBEN SALAS |
| Permit Finaled | 7/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/4/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 11/5/2024 | ASHLEY RODARTE |
| Public Works-Highway Ded. | Cleared | 11/5/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 3/11/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/4/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 11/12/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/12/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/9/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/9/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 12/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 1/16/2026 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 1/16/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Wood Frame | 1/16/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 1/22/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/28/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/20/2026 | Approved | JOSE AVILA |
| Shower Pan | 2/20/2026 | Approved | JOSE AVILA |
| Sewer | 4/3/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/28/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 5/28/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 5/28/2026 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Approved | MICHAEL CORTEZ |
| Smoke Detectors | 5/28/2026 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 6/5/2026 | Approved | JENNIFER RABUCHIN |
| Final | 6/5/2026 | OK to Issue CofO | JENNIFER RABUCHIN |