1648-1650 W 69TH ST 90047

Certificate Information: 1648-1650 W 69TH ST 90047

Application / Permit
24016-20000-33954
Plan Check / Job No.
B24VN20733
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMODEL THROUGHOUT (E) DUPLEX. RELOCATE KITCHEN AND ADD NEW BEDROOM AND ONE NEW POWDER ROOM FOR BOTH UNITS.
Permit Issued
Issued on 11/22/2024
Issuing Office
Current Status
Permit Finaled on 7/3/2025

Permit Application Status History

Submitted 10/23/2024 APPLICANT
Assigned to Plan Check Engineer 10/30/2024 JEROME MAGAT PALMA
Corrections Issued 11/1/2024 JEROME MAGAT PALMA
Building Plans Picked Up 11/8/2024 APPLICANT
Plan Check Approved 11/22/2024 SARKIS HARABEDIAN
Issued 11/22/2024 APPLICANT
Permit Finaled 7/2/2025 BARRY HACHE

Permit Application Clearance Information

Sewer availability Cleared 11/12/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/15/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2025 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 1/13/2025 Approved BARRY HACHE
ELECTRICAL-Rough 2/25/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 2/25/2025 Corrections Issued BARRY HACHE
Wood Frame 2/25/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 3/4/2025 Not Ready for Inspection JOSE MACIAS
Interior/Exterior Lathing 3/4/2025 Not Ready for Inspection JOSE MACIAS
BUILDING-Rough-Frame 3/12/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 3/12/2025 Corrections Issued BARRY HACHE
HVAC-Rough 3/12/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 3/12/2025 Approved BARRY HACHE
PLUMBING-Rough 3/12/2025 Corrections Issued BARRY HACHE
Wood Frame 3/12/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 3/14/2025 Partial Approval JOHN QUINTANILLA
Gas Test 3/14/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/14/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/14/2025 Partial Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 3/17/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/17/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/17/2025 Approved ENRIQUE MIRELES
Wood Frame 3/17/2025 Approved ENRIQUE MIRELES
Insulation 3/18/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued BARRY HACHE
Insulation 3/25/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Approved BARRY HACHE
Drywall Nailing 4/4/2025 Approved BARRY HACHE
Final 6/3/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 6/3/2025 Approved BARRY HACHE
ELECTRICAL-Final 6/5/2025 Corrections Issued BARRY HACHE
HVAC-Final 6/5/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 6/5/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 6/17/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 6/17/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 6/17/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 6/25/2025 Not Ready for Inspection BARRY HACHE
Final 6/25/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 6/25/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 6/25/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready BARRY HACHE
ELECTRICAL-Final 6/26/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 6/26/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 7/2/2025 Approved BARRY HACHE
Final 7/2/2025 Permit Finaled BARRY HACHE
HVAC-Final 7/2/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 7/2/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved BARRY HACHE
Service/Power Release 7/2/2025 Approved BARRY HACHE