7447 1/2 N IRVINE AVE 91605

Certificate Information: 7447 1/2 N IRVINE AVE 91605

Application / Permit
24016-20000-33911
Plan Check / Job No.
B24VN20690
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: GARAGE CONVERSION TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 JOSEPH RAFOLS
Corrections Issued 11/1/2024 JOSEPH RAFOLS
Applicant returned to address corrections 12/7/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 12/18/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 1/24/2025 NEHEMIAS RAMOS
Plan Check Approved 2/13/2025 NEHEMIAS RAMOS
Issued 3/10/2025 APPLICANT
CofO in Progress 9/3/2025 ROBERTO PALACIOS-LOPEZ
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/9/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/9/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/9/2024 RYAN CASTRO
Sewer availability Cleared 12/9/2024 RYAN CASTRO

Contact Information

Contractor Advanced Aluminum Awning Co; Lic. No.: 575140-B       ,
Contractor Anderson V E Inc; Lic. No.: 575140-B       ,
Engineer Dong,, Truong; Lic. No.: C75466 10692 SILVER CIRCLE      GARDEN GROVE, CA 92843

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Sewer 3/27/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 4/1/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/18/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/18/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Wood Frame 6/18/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/7/2025 Partial Approval JOSE AVILA
Insulation 7/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/11/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 8/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 8/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 8/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/28/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/28/2025 Approved ROBERTO PALACIOS-LOPEZ