7447 1/2 N IRVINE AVE 91605
Certificate Information: 7447 1/2 N IRVINE AVE 91605
- Application / Permit
- 24016-20000-33911
- Plan Check / Job No.
- B24VN20690
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: GARAGE CONVERSION TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 3/10/2025
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | JOSEPH RAFOLS |
| Corrections Issued | 11/1/2024 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/7/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/18/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 1/24/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/13/2025 | NEHEMIAS RAMOS |
| Issued | 3/10/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 9/25/2025 | RUBEN SALAS |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 12/9/2024 | RYAN CASTRO |
Contact Information
| Contractor | Advanced Aluminum Awning Co; Lic. No.: 575140-B | , |
| Contractor | Anderson V E Inc; Lic. No.: 575140-B | , |
| Engineer | Dong,, Truong; Lic. No.: C75466 | 10692 SILVER CIRCLE GARDEN GROVE, CA 92843 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/27/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Sewer | 3/27/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 3/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 4/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 6/18/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 6/18/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 6/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/7/2025 | Partial Approval | JOSE AVILA |
| Insulation | 7/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/11/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 8/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/28/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |