5500 W WILSHIRE BLVD 90036
Certificate Information: 5500 W WILSHIRE BLVD 90036
- Application / Permit
- 24016-20000-33741
- Plan Check / Job No.
- B24VN20511
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- COMMERCIAL TI ON 6TH, 7TH, 8TH FLOOR @ OFFICE SPACE # 600, 700, 800.
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/4/2025
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2024 | JESSE ARELLANO |
| Corrections Issued | 10/29/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 10/31/2024 | APPLICANT |
| Issued | 11/7/2024 | APPLICANT |
| Permit Finaled | 2/3/2025 | MARTIN TAVITIAN |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 11/4/2024 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 11/4/2024 | LAMBERT GIESSINGER |
| Redevelopment Project Area | Cleared | 11/5/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 11/8/2024 | Approved | MARTIN TAVITIAN |
| Light Gage Steel Frame | 11/8/2024 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 11/13/2024 | Approved | MARTIN TAVITIAN |
| Final | 12/10/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Required | MARTIN TAVITIAN |
| Smoke Detectors | 12/10/2024 | Approved | MARTIN TAVITIAN |
| Final | 2/3/2025 | Permit Finaled | MARTIN TAVITIAN |