10566-10568 N MARKLEIN AVE 91345

Certificate Information: 10566-10568 N MARKLEIN AVE 91345

Application / Permit
24016-20000-33733
Plan Check / Job No.
B24VN20505
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing attached garage to ADU per CA Govt. Code 65852.2(e)(1)(A). Design per WFPP.
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/25/2024 CAROLEAN BASMA
Corrections Issued 10/28/2024 CAROLEAN BASMA
Plan Check Approved 11/15/2024 CAROLEAN BASMA
Issued 1/8/2025 APPLICANT
CofO in Progress 6/30/2025 JENNIFER RABUCHIN
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/5/2024 CARLOS RAMIREZ
Sewer availability Cleared 11/5/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/12/2024 CARLOS RAMIREZ
Watercourse Cleared 11/12/2024 CARLOS RAMIREZ

Contact Information

Contractor Winter Remodeling Inc; Lic. No.: 1082865-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/17/2025 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/28/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 1/28/2025 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 2/3/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/3/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 2/6/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/14/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/14/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 2/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/14/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/19/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/19/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/19/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 2/28/2025 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 2/28/2025 Partial Approval JENNIFER RABUCHIN
Insulation 3/7/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/11/2025 Approved KEVIN BERBERYAN
Drywall Nailing 3/14/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Approved JENNIFER RABUCHIN
Shower Pan 4/14/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/1/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/2/2025 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 6/2/2025 Partial Approval JENNIFER RABUCHIN
MERV13>=Final 6/2/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/2/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Not Ready JENNIFER RABUCHIN
Sewer 6/2/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 6/2/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/25/2025 Approved JENNIFER RABUCHIN
Final 6/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Final 6/25/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/25/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready JENNIFER RABUCHIN
Final 6/30/2025 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 6/30/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved JENNIFER RABUCHIN