6701 N OAKDALE AVE 91306

Certificate Information: 6701 N OAKDALE AVE 91306

Application / Permit
24016-20000-33714
Plan Check / Job No.
B24VN20474
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/25/2024 DANIEL ABRAMYAN
Corrections Issued 10/28/2024 DANIEL ABRAMYAN
Plan Check Approved 11/8/2024 OMAR GARNICA
Issued 11/21/2024 APPLICANT
CofO in Progress 9/8/2025 ALEXANDER HANDY
Permit Finaled 10/2/2025 MICHAEL PELHAM
CofO Issued 10/2/2025 MICHAEL PELHAM
Permit Finaled 10/2/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/29/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 10/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 10/29/2024 EDGAR ALCARAZ

Contact Information

Contractor T & A Construction Inc; Lic. No.: 1099128-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/23/2025 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 1/28/2025 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 2/21/2025 Approved ALEXANDER HANDY
Pre-Inspection 4/14/2025 Partial Inspection ALEXANDER HANDY
PLUMBING-Rough 5/6/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Conditional Approval GEVORK IPCHYAN
ELECTRICAL-Rough 5/15/2025 Corrections Issued SCOTT SOBEL
HVAC-Rough 5/15/2025 Not Ready for Inspection SCOTT SOBEL
PLUMBING-Rough 5/15/2025 Approved SCOTT SOBEL
Deputy Wood Construction 5/16/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 6/18/2025 Conditional Approval ALEXANDER HANDY
ELECTRICAL-Rough 6/18/2025 Approved ALEXANDER HANDY
HVAC-Rough 6/18/2025 Approved ALEXANDER HANDY
Insulation 6/18/2025 Corrections Issued ALEXANDER HANDY
Underground Mechanical 6/26/2025 Corrections Issued SCOTT SOBEL
Interior/Exterior Lathing 7/2/2025 Approved SCOTT SOBEL
Shower Pan 7/2/2025 Approved SCOTT SOBEL
Underground Mechanical 7/2/2025 Partial Approval SCOTT SOBEL
ELECTRICAL-Rough 7/9/2025 Approved ALEXANDER HANDY
Drywall Nailing 7/18/2025 Approved ALEXANDER HANDY
Green Building Rough 7/18/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 8/19/2025 Approved ALEXANDER HANDY
Final 8/19/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 8/19/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 8/19/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 9/4/2025 Approved ALEXANDER HANDY
Final 9/4/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 9/4/2025 Approved ALEXANDER HANDY
HVAC-Final 9/4/2025 Approved ALEXANDER HANDY
PLUMBING-Final 9/4/2025 Approved ALEXANDER HANDY