6701 N OAKDALE AVE 91306
Certificate Information: 6701 N OAKDALE AVE 91306
- Application / Permit
- 24016-20000-33714
- Plan Check / Job No.
- B24VN20474
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 10/28/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 11/8/2024 | OMAR GARNICA |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 9/8/2025 | ALEXANDER HANDY |
| Permit Finaled | 10/2/2025 | MICHAEL PELHAM |
| CofO Issued | 10/2/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/2/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 10/29/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | T & A Construction Inc; Lic. No.: 1099128-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/23/2025 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/28/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 2/21/2025 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 4/14/2025 | Partial Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 5/6/2025 | Partial Approval | SCOTT SOBEL |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Conditional Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 5/15/2025 | Corrections Issued | SCOTT SOBEL |
| HVAC-Rough | 5/15/2025 | Not Ready for Inspection | SCOTT SOBEL |
| PLUMBING-Rough | 5/15/2025 | Approved | SCOTT SOBEL |
| Deputy Wood Construction | 5/16/2025 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 6/18/2025 | Conditional Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/18/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 6/18/2025 | Approved | ALEXANDER HANDY |
| Insulation | 6/18/2025 | Corrections Issued | ALEXANDER HANDY |
| Underground Mechanical | 6/26/2025 | Corrections Issued | SCOTT SOBEL |
| Interior/Exterior Lathing | 7/2/2025 | Approved | SCOTT SOBEL |
| Shower Pan | 7/2/2025 | Approved | SCOTT SOBEL |
| Underground Mechanical | 7/2/2025 | Partial Approval | SCOTT SOBEL |
| ELECTRICAL-Rough | 7/9/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 7/18/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 7/18/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | ALEXANDER HANDY |
| Final | 8/19/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 8/19/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 8/19/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| Final | 9/4/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/4/2025 | Approved | ALEXANDER HANDY |