6945 N QUAKERTOWN AVE 91306

Certificate Information: 6945 N QUAKERTOWN AVE 91306

Application / Permit
24016-20000-33710
Plan Check / Job No.
B24VN20467
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 12/11/2024
Issuing Office
Current Status
CofO Issued on 9/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/28/2024 ARTIN ZARUKIAN
Corrections Issued 10/31/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/1/2024 APPLICANT
Plan Check Approved 12/11/2024 ROSENDO MEDINA
Issued 12/11/2024 APPLICANT
CofO in Progress 8/11/2025 ALEXANDER HANDY
Permit Finaled 9/2/2025 JOHN JANSON
CofO Issued 9/2/2025 JOHN JANSON
Permit Finaled 9/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/7/2024 CARLOS AGUILERA
Sewer availability Cleared 11/7/2024 CARLOS AGUILERA
ZI Cleared 11/7/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 11/8/2024 CARLOS AGUILERA

Contact Information

Contractor Vision Adu Llc; Lic. No.: 1115842-B 405 S MISSION DR      SAN GABRIEL, CA 91776
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/11/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 3/11/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 3/11/2025 Partial Approval ALEXANDER HANDY
Deputy Drilled-In Anchors 3/12/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 4/1/2025 Corrections Issued HENRY KIM
ELECTRICAL-Rough 4/1/2025 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 4/1/2025 Corrections Issued HENRY KIM
Sewer 4/1/2025 Approved HENRY KIM
BUILDING-Rough-Frame 4/23/2025 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 4/23/2025 Approved ALEXANDER HANDY
Green Building Rough 4/23/2025 Approved ALEXANDER HANDY
HVAC-Rough 4/23/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 4/23/2025 Approved ALEXANDER HANDY
Insulation 4/29/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 5/5/2025 Approved ALEXANDER HANDY
Drywall Nailing 5/5/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 5/14/2025 Corrections Issued SCOTT SOBEL
Shower Pan 5/14/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 5/27/2025 Approved ALEXANDER HANDY
ELECTRICAL-Rough 7/11/2025 Corrections Issued ALEXANDER HANDY
Final 7/25/2025 Corrections Issued KRISTEN CAUSEY
Final 8/4/2025 No Access for Inspection KRISTEN CAUSEY
Green Building Final 8/4/2025 No Access for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 8/4/2025 No Access for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 8/8/2025 Approved ALEXANDER HANDY
Final 8/8/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 8/8/2025 Approved ALEXANDER HANDY
HVAC-Final 8/8/2025 Approved ALEXANDER HANDY
PLUMBING-Final 8/8/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 8/8/2025 Approved ALEXANDER HANDY