6599-6601 N NEDDY AVE 91307

Certificate Information: 6599-6601 N NEDDY AVE 91307

Application / Permit
24016-20000-33708
Plan Check / Job No.
B24VN20466
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO A (N) ADU PER GCS 65852.2(e)(1)(A) PER WFPP
Permit Issued
Issued on 11/6/2024
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 LUISANGEL VALENZUELA
Corrections Issued 10/25/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/29/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/31/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 11/3/2024 SEWADA ZADOORAN MILAGARDI
Issued 11/6/2024 APPLICANT
CofO in Progress 12/24/2024 TROY SANDERS
No Progress 1/2/2025 HENRY KIM
CofO in Progress 1/2/2025 HENRY KIM
Permit Finaled 2/6/2025 JOHN JANSON
CofO Issued 2/6/2025 JOHN JANSON
Permit Finaled 2/6/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/25/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/25/2024 BIAINA HARITUNIAN

Contact Information

Contractor S & T Builders; Lic. No.: 1090121-B       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/13/2024 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 11/14/2024 Approved GEVORK IPCHYAN
Sewer 11/14/2024 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 11/15/2024 Conditional Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 11/25/2024 Approved GEVORK IPCHYAN
HVAC-Rough 11/25/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 11/25/2024 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 11/25/2024 Approved GEVORK IPCHYAN
Shower Pan 11/25/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 11/27/2024 Approved GEVORK IPCHYAN
Insulation 11/27/2024 Approved GEVORK IPCHYAN
Shower Pan 11/27/2024 Approved GEVORK IPCHYAN
Special/Order Compliance 11/27/2024 Approved SCOTT SOBEL
Drywall Nailing 12/2/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 12/2/2024 Partial Approval GEVORK IPCHYAN
Final 12/23/2024 OK to Issue CofO TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 12/23/2024 Approved TROY SANDERS
Special/Order Compliance 1/2/2025 Corrections Issued GEVORK IPCHYAN