6849 N RHEA AVE 91335
Certificate Information: 6849 N RHEA AVE 91335
- Application / Permit
- 24016-20000-33418
- Plan Check / Job No.
- B24VN20280
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert existing detach 19'.10" x18'.2" garage to Accessory Dwelling Unit per GCS 65852.2 (e)(1)(A), WFPP.
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | TSE MING HUANG |
| Corrections Issued | 11/1/2024 | TSE MING HUANG |
| Applicant returned to address corrections | 1/30/2025 | TSE MING HUANG |
| Plan Check Approved | 2/25/2025 | TSE MING HUANG |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 1/27/2026 | JOHN JANSON |
| CofO Issued | 1/27/2026 | JOHN JANSON |
| Permit Finaled | 1/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| ZI | Cleared | 2/11/2025 | FIPE LEILUA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 3/11/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 3/13/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/11/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/11/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 4/18/2025 | Corrections Issued | ROBERT GOLD |
| Interior/Exterior Lathing | 4/18/2025 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 4/18/2025 | Corrections Issued | ROBERT GOLD |
| Insulation | 4/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/24/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/29/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/29/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 4/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 7/21/2025 | Approved | JUAN ALVARADO |
| Pre-Inspection | 8/25/2025 | Partial Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 10/23/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 10/27/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 11/17/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/5/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/5/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/5/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 1/5/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/5/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 1/5/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/12/2026 | Approved | ARUTYUN MADATYAN |
| Final | 1/12/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 1/12/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 1/12/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/12/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 1/12/2026 | Approved | ARUTYUN MADATYAN |