1775 S FAIRFAX AVE 90019
Certificate Information: 1775 S FAIRFAX AVE 90019
- Application / Permit
- 24016-20000-33168
- Plan Check / Job No.
- B24VN20016
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- Issued on 11/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 10/28/2024 | ARTIN ZARUKIAN |
| Plan Check Approved | 10/29/2024 | YAQUB MIRZA |
| Building Plans Picked Up | 10/29/2024 | APPLICANT |
| Issued | 11/19/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 10/29/2024 | TREVOR QUAN |
Contact Information
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 1/21/2025 | Approved | ARTHUR NEGRETE |
| Deputy Drilled-In Anchors | 1/22/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 1/27/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 2/7/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 2/7/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 2/7/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 2/7/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 2/11/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | ALEX COLIN |
| Shower Pan | 2/11/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 2/20/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/20/2025 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 2/24/2025 | Approved | ALEX COLIN |
| Gas Test | 4/14/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 4/14/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/14/2025 | Approved | ARTHUR NEGRETE |
| Final | 4/17/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 4/17/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/21/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/21/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/21/2025 | Approved | ARTHUR NEGRETE |