21034-21036 W LULL ST 91304

Certificate Information: 21034-21036 W LULL ST 91304

Application / Permit
24016-20000-33086
Plan Check / Job No.
B24VN19938
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN EXISTING GARAGE TO BE CONVERTED INTO ATTACHED ACCESSORY DWELLING UNIT PER STATE LAW and GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/10/2025
Issuing Office
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2024 APPLICANT
Assigned to Plan Check Engineer 10/21/2024 ZAW HAN
Corrections Issued 10/22/2024 ZAW HAN
Applicant returned to address corrections 12/3/2024 ZAW HAN
Applicant returned to address corrections 1/22/2025 ZAW HAN
Applicant returned to address corrections 2/8/2025 ZAW HAN
Plan Check Approved 2/10/2025 ZAW HAN
Issued 2/10/2025 APPLICANT
CofO in Progress 7/16/2025 ALEXANDER HANDY
Permit Finaled 8/20/2025 JOHN JANSON
CofO Issued 8/20/2025 JOHN JANSON
Permit Finaled 8/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/26/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 11/26/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/26/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/7/2025 LEE GUILBEAUX
Permit Cleared 1/7/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2025 Partial Inspection ALEXANDER HANDY
Deputy Drilled-In Anchors 3/11/2025 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 3/11/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 3/11/2025 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 4/17/2025 Approved ALEXANDER HANDY
Gas Test 4/17/2025 Partial Approval ALEXANDER HANDY
HVAC-Rough 4/17/2025 Approved ALEXANDER HANDY
PLUMBING-Final 4/17/2025 Approved ALEXANDER HANDY
Wood Frame 4/17/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 4/24/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 4/24/2025 Partial Approval ALEXANDER HANDY
Insulation 4/24/2025 Corrections Issued ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved ALEXANDER HANDY
Insulation 4/30/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/30/2025 Partial Approval ALEXANDER HANDY
Drywall Nailing 5/8/2025 Approved ALEXANDER HANDY
Final 6/27/2025 Corrections Issued KRISTEN CAUSEY
BUILDING-Rough-Frame 7/14/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 7/14/2025 Approved ALEXANDER HANDY
Final 7/14/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 7/14/2025 Approved ALEXANDER HANDY
Green Building Rough 7/14/2025 Approved ALEXANDER HANDY
HVAC-Final 7/14/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 7/14/2025 Approved ALEXANDER HANDY