3466 W GARDEN AVE 90039

Certificate Information: 3466 W GARDEN AVE 90039

Application / Permit
24016-20000-32657
Plan Check / Job No.
B24VN19646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). WORK DONE PER ENGINEER DESIGN. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2024 APPLICANT
Assigned to Plan Check Engineer 10/21/2024 JEROME MAGAT PALMA
Corrections Issued 10/23/2024 JEROME MAGAT PALMA
Building Plans Picked Up 10/25/2024 APPLICANT
Applicant returned to address corrections 1/30/2025 MADISON ODELL
Applicant returned to address corrections 2/27/2025 GIOVANNY CHAVEZ
Plan Check Approved 3/10/2025 MADISON O'DELL
Issued 3/12/2025 APPLICANT
CofO in Progress 6/5/2026 NICHOLAS LOPEZ
Permit Finaled 6/8/2026 DEROLD HAUFF
CofO Issued 6/8/2026 DEROLD HAUFF
Permit Finaled 6/8/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 10/28/2024 ALEX VELA
Address approval Cleared 10/30/2024 ADRIAN SANCHEZ
Sewer availability Cleared 10/30/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 12/30/2024 ADRIAN SANCHEZ
Construction near power lines Cleared 2/12/2025 WALTER RAMIREZ

Contact Information

Contractor Opus Builders Inc; Lic. No.: 1059646-B 5244 VINELAND AVENUE      NORTH HOLLYWOOD, CA 91601
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 4/29/2025 Partial Approval NICHOLAS LOPEZ
Underground Mechanical 8/29/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 9/24/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 9/24/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 9/24/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 9/24/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 9/24/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 9/24/2025 Approved NICHOLAS LOPEZ
Insulation 10/9/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 10/21/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 10/21/2025 Approved NICHOLAS LOPEZ
Shower Pan 10/21/2025 Approved NICHOLAS LOPEZ
Final 5/29/2026 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 5/29/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 5/29/2026 Not Ready for Inspection CRAIG VAUGHAN
Final 6/5/2026 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/5/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 6/5/2026 Approved NICHOLAS LOPEZ