3466 W GARDEN AVE 90039
Certificate Information: 3466 W GARDEN AVE 90039
- Application / Permit
- 24016-20000-32657
- Plan Check / Job No.
- B24VN19646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). WORK DONE PER ENGINEER DESIGN. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 10/23/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/25/2024 | APPLICANT |
| Applicant returned to address corrections | 1/30/2025 | MADISON ODELL |
| Applicant returned to address corrections | 2/27/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/10/2025 | MADISON O'DELL |
| Issued | 3/12/2025 | APPLICANT |
| CofO in Progress | 6/5/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
| CofO Issued | 6/8/2026 | DEROLD HAUFF |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 10/28/2024 | ALEX VELA |
| Address approval | Cleared | 10/30/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/30/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 2/12/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Opus Builders Inc; Lic. No.: 1059646-B | 5244 VINELAND AVENUE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 9/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 10/9/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 5/29/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/5/2026 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 6/5/2026 | Approved | NICHOLAS LOPEZ |