1917 N AVENUE 52 90042
Certificate Information: 1917 N AVENUE 52 90042
- Application / Permit
- 24016-20000-32631
- Plan Check / Job No.
- B24VN19604
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 09/19/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 10/19/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/25/2024 | APPLICANT |
| Plan Check Approved | 11/8/2024 | SARKIS HARABEDIAN |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 8/11/2025 | DANIEL DELACRUZ |
| CofO Issued | 8/28/2025 | DANIEL SANCHEZ |
| Permit Finaled | 8/28/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/5/2024 | MICHAEL TEMPLE |
| Address approval | Cleared | 11/6/2024 | WALLIE JONG |
| Sewer availability | Cleared | 11/6/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Asprer,, Anjero; Lic. No.: C91126 | 2708 FOOTHILL BLVD. #1006 LA CRESCENTA, CA 91214 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2024 | Partial Inspection | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Approved | DANIEL DELACRUZ |
| Pre-Inspection | 12/19/2024 | Approved | DANIEL DELACRUZ |
| Wood Frame | 1/17/2025 | Approved | PEDRO SIERRA |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | DANIEL DELACRUZ |
| Wood Frame | 1/29/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 2/20/2025 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 2/20/2025 | Approved | DANIEL DELACRUZ |
| Wood Frame | 2/20/2025 | Conditional Approval | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 3/6/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 3/6/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 3/6/2025 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | DANIEL DELACRUZ |
| Insulation | 3/26/2025 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 3/26/2025 | Approved | DANIEL DELACRUZ |
| Underground Mechanical | 3/26/2025 | Approved | DANIEL DELACRUZ |
| Drywall Nailing | 4/2/2025 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 4/2/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Final | 7/25/2025 | Approved | DANIEL DELACRUZ |
| Final | 7/25/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | DANIEL DELACRUZ |
| Smoke Detectors | 7/25/2025 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Final | 8/7/2025 | Approved | DANIEL DELACRUZ |
| Final | 8/7/2025 | OK to Issue CofO | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | DANIEL DELACRUZ |