1917 N AVENUE 52 90042

Certificate Information: 1917 N AVENUE 52 90042

Application / Permit
24016-20000-32631
Plan Check / Job No.
B24VN19604
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 09/19/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/12/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2024 APPLICANT
Assigned to Plan Check Engineer 10/18/2024 ARTIN ZARUKIAN
Corrections Issued 10/19/2024 ARTIN ZARUKIAN
Building Plans Picked Up 10/25/2024 APPLICANT
Plan Check Approved 11/8/2024 SARKIS HARABEDIAN
Issued 11/12/2024 APPLICANT
CofO in Progress 8/11/2025 DANIEL DELACRUZ
CofO Issued 8/28/2025 DANIEL SANCHEZ
Permit Finaled 8/28/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/5/2024 MICHAEL TEMPLE
Address approval Cleared 11/6/2024 WALLIE JONG
Sewer availability Cleared 11/6/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/7/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Asprer,, Anjero; Lic. No.: C91126 2708 FOOTHILL BLVD. #1006      LA CRESCENTA, CA 91214

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2024 Partial Inspection DANIEL DELACRUZ
Excavation/Setback/Form/Re-Bar 12/19/2024 Approved DANIEL DELACRUZ
Pre-Inspection 12/19/2024 Approved DANIEL DELACRUZ
Wood Frame 1/17/2025 Approved PEDRO SIERRA
Interior/Exterior Lathing 1/29/2025 Partial Approval DANIEL DELACRUZ
Wood Frame 1/29/2025 Not Ready for Inspection DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved DANIEL DELACRUZ
HVAC-Rough 2/20/2025 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 2/20/2025 Approved DANIEL DELACRUZ
Wood Frame 2/20/2025 Conditional Approval DANIEL DELACRUZ
ELECTRICAL-Rough 3/6/2025 Approved DANIEL DELACRUZ
HVAC-Rough 3/6/2025 Approved DANIEL DELACRUZ
PLUMBING-Rough 3/6/2025 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 3/26/2025 Approved DANIEL DELACRUZ
Insulation 3/26/2025 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 3/26/2025 Approved DANIEL DELACRUZ
Underground Mechanical 3/26/2025 Approved DANIEL DELACRUZ
Drywall Nailing 4/2/2025 Approved DANIEL DELACRUZ
Smoke Detectors 4/2/2025 Not Ready for Inspection DANIEL DELACRUZ
ELECTRICAL-Final 7/25/2025 Approved DANIEL DELACRUZ
Final 7/25/2025 Not Ready for Inspection DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready DANIEL DELACRUZ
Smoke Detectors 7/25/2025 Approved DANIEL DELACRUZ
ELECTRICAL-Final 8/7/2025 Approved DANIEL DELACRUZ
Final 8/7/2025 OK to Issue CofO DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved DANIEL DELACRUZ