114 W 43RD PL 90037

Certificate Information: 114 W 43RD PL 90037

Application / Permit
24016-20000-32551
Plan Check / Job No.
B24VN19513
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN:: Convert detached 2-story garage and storage into 2- story accessory dwelling unit per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/21/2025
Issuing Office
Current Status
Issued on 4/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/11/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 SERGIO MUNIZ
Corrections Issued 10/17/2024 SERGIO MUNIZ
Applicant returned to address corrections 12/4/2024 KAMYAR EMAMI
Applicant returned to address corrections 12/19/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/19/2024 SERGIO MUNIZ
Applicant returned to address corrections 12/23/2024 MOHAMMAD ESMAILI
Plan Check Approved 12/28/2024 MOHAMMAD ESMAILI
No Progress 4/17/2025 MOHAMMAD ESMAILI
Plan Check Approved 4/17/2025 MOHAMMAD ESMAILI
Issued 4/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/26/2024 ADRIAN SANCHEZ
Sewer availability Cleared 10/26/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 10/31/2024 JEANIE LAM
Community Plan Implem. Overlay Cleared 11/5/2024 ANACANY HURTADO
Miscellaneous Cleared 11/7/2024 DAVID URITA
Historic Resource Verification Cleared 11/13/2024 RAFAEL FONTES
Redevelopment Project Area Cleared 11/14/2024 YASMINE BASHIRI

Contact Information

Contractor Zvik Sahar; Lic. No.: 1081253-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 6/18/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/26/2025 Approved LUIS CASTRO
PLUMBING-Rough 6/26/2025 Not Ready for Inspection LUIS CASTRO
Underground Mechanical 6/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 7/2/2025 Partial Approval JOHN QUINTANILLA
Deputy Wood Construction 8/29/2025 Conditional Approval ALEJANDRO DE ARTOLA
Pre-Inspection 8/29/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Corrections Issued BARRY HACHE
Gas Test 9/8/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 9/8/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 9/8/2025 Not Ready for Inspection BARRY HACHE
Deputy Wood Construction 9/9/2025 Conditional Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/16/2025 Conditional Approval RONNIE MEDINA
BUILDING-Rough-Frame 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/6/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/6/2025 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/9/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 10/9/2025 No Access for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 10/10/2025 Approved ENRIQUE MIRELES
Wood Frame 10/10/2025 Approved ENRIQUE MIRELES
Insulation 10/15/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 10/20/2025 Approved GEM DE OCAMPO
Gas Test 12/24/2025 Corrections Issued LUIS CASTRO
Underground Mechanical 1/9/2026 Corrections Issued MICHAEL LEWIS
Underground Mechanical 1/16/2026 Corrections Issued ALEJANDRO DE ARTOLA