20047 W PARTHENIA ST 91324

Certificate Information: 20047 W PARTHENIA ST 91324

Application / Permit
24016-20000-32508
Plan Check / Job No.
B24VN19471
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Detached garage conversion to an ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/11/2024
Issuing Office
Current Status
CofO Issued on 4/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/16/2024 DAVID CASTILLO
Corrections Issued 10/16/2024 DAVID CASTILLO
Plan Check Approved 11/11/2024 REZA HAGHIGHAT
Issued 12/11/2024 APPLICANT
CofO in Progress 4/18/2025 JEFFREY HARTLINE
Permit Finaled 4/29/2025 JOHN JANSON
CofO Issued 4/29/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/20/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/20/2024 LEE GUILBEAUX
Sewer availability Cleared 10/20/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/20/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/21/2024 LEE GUILBEAUX

Contact Information

Contractor Oro Coast Builders Inc; Lic. No.: 1063640-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/9/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 1/9/2025 Approved JEFFREY HARTLINE
Pre-Inspection 1/9/2025 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 1/14/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/29/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/29/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Partial Approval JEFFREY HARTLINE
HVAC-Rough 1/29/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/29/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 2/10/2025 Approved JEFFREY HARTLINE
HVAC-Rough 2/10/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/10/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 2/10/2025 Not Ready for Inspection JEFFREY HARTLINE
Wood Frame 2/10/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 2/12/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 2/12/2025 Approved JEFFREY HARTLINE
Insulation 2/19/2025 Conditional Approval CHRIS CHRISTENSEN
Wood Frame 2/19/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 2/25/2025 Approved CHRIS CHRISTENSEN
Shower Pan 2/25/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/28/2025 Approved JEFFREY HARTLINE
Green Building Rough 2/28/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/28/2025 Partial Approval JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Ready JEFFREY HARTLINE
ELECTRICAL-Final 4/14/2025 Approved JEFFREY HARTLINE
Final 4/14/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/14/2025 Approved JEFFREY HARTLINE
HVAC-Final 4/14/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 4/14/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Not Ready JEFFREY HARTLINE
Service/Power Release 4/14/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 4/14/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 4/18/2025 Approved JEFFREY HARTLINE
Final 4/18/2025 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 4/18/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 4/18/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 4/18/2025 Approved JEFFREY HARTLINE
Smoke Detectors 4/18/2025 Approved JEFFREY HARTLINE