8052 N LAUREL CANYON BLVD 91605
Certificate Information: 8052 N LAUREL CANYON BLVD 91605
- Application / Permit
- 24016-20000-32496
- Plan Check / Job No.
- B24VN19457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] (E) GARAGE CONVERT TO NEW ADU PER CA Govt. Code 65852.2(e)(1)(A) CUGU- PUBLICLY HABITABLE SPACE
- Permit Issued
- Issued on 11/28/2024
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/30/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/8/2024 | TU HUA |
| Applicant returned to address corrections | 11/26/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/27/2024 | MAHNAZ NOURHASHEMI |
| Issued | 11/28/2024 | APPLICANT |
| CofO in Progress | 2/26/2026 | MATTHEW NELSON |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/7/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 11/12/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/12/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | DAVID MATSON |
| Green Building Rough | 9/8/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/8/2025 | Partial Approval | MATTHEW NELSON |
| Pre-Inspection | 9/8/2025 | Approved | MATTHEW NELSON |
| Insulation | 9/16/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/23/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/14/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 2/20/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/20/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 2/20/2026 | Approved | MATTHEW NELSON |
| Wood Frame | 2/20/2026 | Approved | MATTHEW NELSON |
| Final | 2/25/2026 | OK to Issue CofO | MATTHEW NELSON |