9757-9759 N COLUMBUS AVE 91343
Certificate Information: 9757-9759 N COLUMBUS AVE 91343
- Application / Permit
- 24016-20000-32461
- Plan Check / Job No.
- B24VN19417
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Convert existing family room into JADU (487 SF) in existing 1 story single family dwelling per State Law, CA Govt. Code 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- CofO Issued on 7/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2024 | AUNG SOE |
| Corrections Issued | 10/17/2024 | AUNG SOE |
| Applicant returned to address corrections | 10/29/2024 | ZAW HAN |
| Applicant returned to address corrections | 10/30/2024 | ZAW HAN |
| Plan Check Approved | 11/15/2024 | ADAM HEGAZI |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 5/13/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 7/2/2026 | RUBEN SALAS |
| CofO Issued | 7/2/2026 | RUBEN SALAS |
| Permit Finaled | 7/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 10/22/2024 | NATHAN ROMINE |
| Sewer availability | Cleared | 10/22/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 2/11/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/19/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/21/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 4/21/2026 | No Access for Inspection | JENNIFER RABUCHIN |
| Final | 4/28/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/13/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | JENNIFER RABUCHIN |