9637 N SUNLAND BLVD 91040

Certificate Information: 9637 N SUNLAND BLVD 91040

Application / Permit
24016-20000-32284
Plan Check / Job No.
B24VN19224
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING PORTION OF RECREATION BUILDING AND COVERED PATIO TO BE ENCLOSED FOR NEW ACCESSORY DWELLING UNIT (870 SF) PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 2/28/2025
Issuing Office
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2024 APPLICANT
Assigned to Plan Check Engineer 10/15/2024 MADISON ODELL
Corrections Issued 10/16/2024 MADISON ODELL
Applicant returned to address corrections 1/21/2025 MADISON ODELL
Plan Check Approved 1/23/2025 ROSENDO MEDINA
Issued 2/28/2025 APPLICANT
CofO in Progress 5/9/2026 DAVID ANDERSON
Permit Finaled 5/29/2026 RUBEN SALAS
CofO Issued 5/29/2026 RUBEN SALAS
Permit Finaled 5/29/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/20/2024 LEE GUILBEAUX
Sewer availability Cleared 10/20/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/20/2024 LEE GUILBEAUX
ZA Case Cleared 10/29/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 10/30/2024 LEE GUILBEAUX
Specific Plan Cleared 11/18/2024 JOSHUA ORDONEZ
Hydrant and Access approval Cleared 1/6/2025 KENNETH FRASER
Grading Pre-Inspection Cleared 1/21/2025 MADISON O'DELL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 9/22/2025 Partial Inspection DAVID ANDERSON
Deputy Drilled-In Anchors 10/3/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 10/8/2025 Approved DAVID ANDERSON
Green Building Rough 10/8/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 11/3/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 1/8/2026 Approved DAVID ANDERSON
HVAC-Rough 1/8/2026 Approved DAVID ANDERSON
PLUMBING-Rough 1/8/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 1/20/2026 Approved DAVID ANDERSON
Green Building Rough 1/20/2026 Approved DAVID ANDERSON
Insulation 1/20/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/20/2026 Partial Approval DAVID ANDERSON
Drywall Nailing 2/3/2026 Approved DAVID ANDERSON
Final 4/15/2026 Corrections Issued DAVID ANDERSON
Green Building Final 4/15/2026 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 4/15/2026 Not Ready for Inspection DAVID ANDERSON
Final 4/28/2026 OK to Issue CofO DAVID ANDERSON
Green Building Final 4/28/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 4/28/2026 Approved DAVID ANDERSON