7800-7802 N VANALDEN AVE 91335
Certificate Information: 7800-7802 N VANALDEN AVE 91335
- Application / Permit
- 24016-20000-31616
- Plan Check / Job No.
- B24VN18589
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 10/10/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/16/2024 | APPLICANT |
| Plan Check Approved | 10/28/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 10/31/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | ARUTYUN MADATYAN |
| CofO Issued | 6/26/2025 | JOHN JANSON |
| Permit Finaled | 6/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/20/2025 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/21/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/12/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | ARUTYUN MADATYAN |
| Gas Test | 3/12/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 3/12/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/12/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Insulation | 3/28/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/5/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Final | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/17/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 6/17/2025 | Approved | ARUTYUN MADATYAN |