916 S VICTORIA AVE 90019
Certificate Information: 916 S VICTORIA AVE 90019
- Application / Permit
- 24016-20000-31442
- Plan Check / Job No.
- B24VN18450
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FIRE DAMAGE REPAIR TO (E) SFD. "COMPLY WITH DEPARTMENT ORDER effective date 7/26/24. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/5/2026
Permit Application Status History
| Submitted | 10/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 10/8/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/11/2024 | APPLICANT |
| Plan Check Approved | 11/13/2024 | SERGIO MUNIZ |
| Issued | 1/23/2025 | APPLICANT |
| Permit Finaled | 2/5/2026 | RUBEN PEREZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/16/2024 | JAZMIN ROQUE |
| CPC | Cleared | 10/16/2024 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/16/2024 | DAVID LOPEZ |
| HPOZ | Cleared | 11/12/2024 | MICAELA TORRES-GIL |
| ZI | Cleared | 11/12/2024 | MICAELA TORRES-GIL |
Contact Information
| Contractor | Tri Tech Restoration & Co; Lic. No.: 501801-B | 3301 N SAN FERNANDO BLVD BURBANK, CA 91504 |
| Engineer | Ameri,, Reza; Lic. No.: C36059 | PO BOX 34979 LOS ANGELES, CA 90034 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/10/2025 | Conditional Approval | PETER RUBIO |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | PETER RUBIO |
| Deputy Reinf. Concrete | 2/12/2025 | Conditional Approval | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | PETER RUBIO |
| Deputy Wood Construction | 3/25/2025 | Conditional Approval | PETER RUBIO |
| Deputy Wood Construction | 3/26/2025 | Conditional Approval | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Rough | 6/27/2025 | Approved | RUBEN PEREZ |
| HVAC-Rough | 6/27/2025 | Approved | RUBEN PEREZ |
| PLUMBING-Rough | 6/27/2025 | Approved | RUBEN PEREZ |
| Wood Frame | 6/27/2025 | Not Ready for Inspection | RUBEN PEREZ |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | RUBEN PEREZ |
| Insulation | 7/7/2025 | Approved | RUBEN PEREZ |
| Interior/Exterior Lathing | 7/7/2025 | Approved | RUBEN PEREZ |
| Drywall Nailing | 7/16/2025 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 7/30/2025 | Approved | PETER RUBIO |
| Shower Pan | 7/30/2025 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 10/7/2025 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Final | 1/27/2026 | Corrections Issued | PETER RUBIO |
| Final | 1/27/2026 | Corrections Issued | PETER RUBIO |
| HVAC-Final | 1/27/2026 | Approved | PETER RUBIO |
| PLUMBING-Final | 1/27/2026 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | PETER RUBIO |
| Smoke Detectors | 1/27/2026 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 1/29/2026 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Final | 2/3/2026 | Not Ready for Inspection | PETER RUBIO |
| Final | 2/3/2026 | Not Ready for Inspection | PETER RUBIO |
| HVAC-Final | 2/3/2026 | Approved | PETER RUBIO |
| PLUMBING-Final | 2/3/2026 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 2/4/2026 | Approved | PETER RUBIO |
| HVAC-Final | 2/4/2026 | Approved | PETER RUBIO |
| PLUMBING-Final | 2/4/2026 | Approved | PETER RUBIO |
| Final | 2/5/2026 | Permit Finaled | RUBEN PEREZ |