15729 W HARTSOOK ST 91436

Certificate Information: 15729 W HARTSOOK ST 91436

Application / Permit
24016-20000-31365
Plan Check / Job No.
B24VN18347
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
CofO Issued on 11/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/7/2024 JEROME MAGAT PALMA
Corrections Issued 10/7/2024 JEROME MAGAT PALMA
Building Plans Picked Up 10/8/2024 APPLICANT
Plan Check Approved 10/23/2024 GURUNATH NESARAJAH
Issued 10/23/2024 APPLICANT
CofO in Progress 9/2/2025 SEAN WIRCH
Permit Finaled 11/8/2025 MICHAEL PELHAM
CofO Issued 11/8/2025 MICHAEL PELHAM
Permit Finaled 11/8/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/8/2024 LEE GUILBEAUX
Sewer availability Cleared 10/8/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/8/2024 LEE GUILBEAUX
Construction within easement Cleared 10/9/2024 EDGAR PASCUA
Eng Process Fee Ord 176,300 Cleared 10/18/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/12/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/13/2024 Partial Approval JON MCHUGH
Deputy Wood Construction 11/26/2024 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 11/26/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 12/11/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 12/18/2024 Approved SEAN WIRCH
HVAC-Rough 12/18/2024 Approved SEAN WIRCH
Special/Order Compliance 12/18/2024 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval SEAN WIRCH
Interior/Exterior Lathing 12/24/2024 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 12/27/2024 Approved SEAN WIRCH
Green Building Rough 12/27/2024 Approved SEAN WIRCH
Interior/Exterior Lathing 12/27/2024 Partial Approval SEAN WIRCH
MERV13>=Rough 12/27/2024 Approved SEAN WIRCH
Insulation 1/2/2025 Approved SEAN WIRCH
Final 9/3/2025 OK to Issue CofO SEAN WIRCH
Green Building Final 9/3/2025 Approved SEAN WIRCH
MERV13>=Final 9/3/2025 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved SEAN WIRCH
Smoke Detectors 9/3/2025 Approved SEAN WIRCH