9324 N ZELZAH AVE 91325
Certificate Information: 9324 N ZELZAH AVE 91325
- Application / Permit
- 24016-20000-31359
- Plan Check / Job No.
- B24VN18341
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Interior / exterior alteration to (e) SFD with att. garage to add 2 bedrooms and 2 bathrooms. All work per WFPP.
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/7/2025
Permit Application Status History
| Submitted | 10/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2024 | REZA HAGHIGHAT |
| Corrections Issued | 10/7/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/16/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/24/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/4/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 11/17/2024 | REZA HAGHIGHAT |
| Issued | 11/19/2024 | APPLICANT |
| Permit Finaled | 1/3/2025 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 10/15/2024 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/4/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/4/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/4/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 12/4/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/4/2024 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 12/4/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/11/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/11/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 12/11/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 12/11/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/17/2024 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 1/3/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/3/2025 | Permit Finaled | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/3/2025 | Approved | JAVIER RAMOS JR |