23562-23564 W KIVIK ST 91367

Certificate Information: 23562-23564 W KIVIK ST 91367

Application / Permit
24016-20000-31356
Plan Check / Job No.
B24VN18337
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. ALL WORK PER WFPP.
Permit Issued
Issued on 11/13/2024
Issuing Office
West Los Angeles
Current Status
Issued on 11/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/4/2024 HAYATO TSUCHIYA
Corrections Issued 10/5/2024 HAYATO TSUCHIYA
Building Plans Picked Up 10/31/2024 APPLICANT
Plan Check Approved 11/13/2024 KAVIAN REFAHI
Issued 11/13/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/1/2024 RYAN CASTRO
Sewer availability Cleared 11/1/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/5/2024 RYAN CASTRO
Grading Pre-Inspection Cleared 11/12/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/22/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 11/22/2024 Not Ready for Inspection GEVORK IPCHYAN
Sewer 11/22/2024 Not Ready for Inspection GEVORK IPCHYAN
Underground Mechanical 11/22/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/6/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 5/6/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/6/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 5/6/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 5/6/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval GEVORK IPCHYAN
HVAC-Rough 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
Insulation 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
Wood Frame 6/13/2025 Corrections Issued GEVORK IPCHYAN
Insulation 7/14/2025 Not Ready for Inspection GEVORK IPCHYAN
Shower Pan 7/14/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 7/31/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 7/31/2025 Approved GEVORK IPCHYAN
Green Building Rough 7/31/2025 Approved GEVORK IPCHYAN
HVAC-Rough 7/31/2025 Approved GEVORK IPCHYAN
Insulation 7/31/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 7/31/2025 Approved GEVORK IPCHYAN
Drywall Nailing 8/5/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 8/5/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 8/5/2025 Approved GEVORK IPCHYAN