448 1/2-450 W SOLANO AVE 90012

Certificate Information: 448 1/2-450 W SOLANO AVE 90012

Application / Permit
24016-20000-31151
Plan Check / Job No.
B24VN18139
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL TO THE (E) DUPLEX.
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
Permit Finaled on 1/31/2025

Permit Application Status History

Submitted 9/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/30/2024 LUISANGEL VALENZUELA
Corrections Issued 9/30/2024 LUISANGEL VALENZUELA
Plan Check Approved 10/23/2024 ALEC MOUSAKHANIAN
Issued 10/23/2024 APPLICANT
Permit Finaled 1/31/2025 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Address approval Cleared 10/21/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/22/2024 WALLIE JONG

Contact Information

Contractor Soul Builders Inc; Lic. No.: 1103425-B 8517 VALLEY FLORES DR      WEST HILLS, CA 91304

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/28/2024 Approved LUIS CASTRO
HVAC-Rough 10/28/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 10/28/2024 Corrections Issued LUIS CASTRO
Wood Frame 10/28/2024 Not Ready for Inspection LUIS CASTRO
Wood Frame 10/29/2024 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 10/30/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 10/30/2024 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 10/30/2024 Approved WILLIAM SIERRA
Special/Order Compliance 10/30/2024 Corrections Issued WILLIAM SIERRA
Wood Frame 11/8/2024 Approved LUIS CASTRO
Insulation 11/13/2024 Approved OSVALDO PARAMO
Shower Pan 11/13/2024 Approved OSVALDO PARAMO
Drywall Nailing 11/25/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 11/25/2024 Approved JOSH MEISTER
Shower Pan 11/25/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 1/7/2025 Approved ALIZAH MAYAGOITIA
Final 1/7/2025 Corrections Issued ALIZAH MAYAGOITIA
MERV13>=Final 1/7/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 1/7/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 1/7/2025 Approved ALIZAH MAYAGOITIA
Final 1/17/2025 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved LILIANA PORTILLO
Final 1/31/2025 Permit Finaled ALIZAH MAYAGOITIA