7430 1/2 N ETON AVE 91303
Certificate Information: 7430 1/2 N ETON AVE 91303
- Application / Permit
- 24016-20000-30996
- Plan Check / Job No.
- B24VN17998
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/25/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/25/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 10/5/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/8/2024 | APPLICANT |
| Plan Check Approved | 10/25/2024 | OMAR GARNICA |
| Issued | 10/25/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/8/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2025 | Approved | HENRY KIM |
| PLUMBING-Rough | 2/18/2025 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 2/27/2025 | Corrections Issued | SCOTT SOBEL |
| BUILDING-Rough-Frame | 4/30/2025 | Corrections Issued | SCOTT SOBEL |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | SCOTT SOBEL |
| Green Building Rough | 4/30/2025 | Not Ready for Inspection | SCOTT SOBEL |
| PLUMBING-Rough | 4/30/2025 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 5/6/2025 | Not Ready for Inspection | SCOTT SOBEL |
| ELECTRICAL-Rough | 5/6/2025 | Partial Approval | SCOTT SOBEL |
| Green Building Rough | 5/6/2025 | Not Ready for Inspection | SCOTT SOBEL |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 6/11/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/11/2025 | Partial Approval | ALEXANDER HANDY |
| Insulation | 6/26/2025 | Approved | SCOTT SOBEL |
| Drywall Nailing | 7/2/2025 | Approved | KRISTEN CAUSEY |
| Final | 12/8/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 5/13/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/13/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/13/2026 | Approved | ALEXANDER HANDY |
| Final | 6/22/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 6/22/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Grounding or Bonding | 6/22/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 6/22/2026 | Approved | ALEXANDER HANDY |