13639 W ERWIN ST 91401
Certificate Information: 13639 W ERWIN ST 91401
- Application / Permit
- 24016-20000-30925
- Plan Check / Job No.
- B24VN17935
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. Convert existing two car garage and patio cover to ADU per State Law
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- Issued on 11/21/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 10/3/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 10/18/2024 | ALEXANDER JOO |
| Plan Check Approved | 11/17/2024 | ALEXANDER JOO |
| Issued | 11/21/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/7/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/28/2024 | RYAN CASTRO |
| Hold | Cleared | 1/14/2025 | TERESA RIVAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 12/5/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/5/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/5/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/31/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 2/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/26/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/26/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/26/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 3/17/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/10/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 7/16/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 7/21/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 7/30/2025 | Approved | MICHAEL CORTEZ |